what is period of de-shuttering for different area of slab
of M25 grade?
Answers were Sorted based on User's Feedback
Answer / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
| Is This Answer Correct ? | 30 Yes | 5 No |
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
how many binding wire can be required for 1 metric tonne steel?
What is cementation
Define absolute co-ordinates?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
Why is loose concrete removed from the surface where new concrete is to be done?
what is the ingrediants of wet mix macadam?construction procedure?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks
Define block?
how much cost of single coat 20mm thick plastering per sqre meter
design data for small rc square water tanks
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)