what is period of de-shuttering for different area of slab
of M25 grade?
Answers were Sorted based on User's Feedback
Answer / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
Is This Answer Correct ? | 30 Yes | 5 No |
Does vetrified tiles needs to be cure before fixing?
IS code for Rolling Margin of steel
why demand factor less then 1 ?
how many tonnes equals to one cubic feet?
what is mix design in mortar mix?
if 20mm & 10mm coarse aggregate we have consider same prapotion than how to analysis m25 concrete
how many nails in 1 sq mitar
What is the difference between Fe 500, Fe 500 D and Fe 515.
How to calculate the Water cement ratio of reqiured compressive Strength of concrete?
how much quantity of blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork. Size-16"x8"x8". Also what is the cement sand ration commonly used?
10 Answers ACC, CCCL, L&T, MFAR, Shoba Devlopers, SLS Developers,
which type of foundation is used for seismic prone area?
9 Answers CCB, Kerala Public Service Commission,
What is the difference between Backfilling & Refilling in Earth Work Group Item ?