what is period of de-shuttering for different area of slab
of M25 grade?
Answers were Sorted based on User's Feedback
Answer / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
| Is This Answer Correct ? | 30 Yes | 5 No |
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
any one tell me what is the volumetric ratio and weigh bathing ratio of 6000 psi concrete. plz help me on this matter.
how to find the cement and sand quantity for wall plastering
What is labor and material payment bond?
How to calculate Cement, Sand and Kapachi required for M20, M25
Define What is rigging?
IF X = Cement ,Fine Aggregate & Coarse Aggregate are in taken in weights for batching. Y= Cement , Fine Aggregate & Coarse Aggregate are taken in volume for batching. Then what will be the relation between X and Y?
what type offoundation suitable for clayey type soil
how many average of shuttering in one cubic meter concrete
what is IS
12 Answers GMR, JMC, JMC Projects,
why +1 to be followed for calculating the no of bars in BBS. Please explain
Define What is the tallest man made structure in the world?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)