How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answers were Sorted based on User's Feedback
For calculating the productivity we have to know the
capacity of Excavator.
Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.
Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)
Therefore, net capacity = 1.22*75%= 0.92 Cum.
time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes
Consider 5 minutes rest taken by the operatoer per hour.
Therefore, no of cycles per hour = 55/0.33 = 165
capacity per hour = 165*0.92 = 151.8 Cum/Hour
In similar fashion for dozer and other equipment can be
calculated.
Is This Answer Correct ? | 139 Yes | 38 No |
Answer / m subbramanian
Along with above calculation, the distance travelled by the machine should also been taken into account.
Is This Answer Correct ? | 44 Yes | 6 No |
Answer / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
Is This Answer Correct ? | 29 Yes | 5 No |
Answer / ashebir
calculation for productivity of construction equipment
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / mickey
There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / mandar
i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).
Is This Answer Correct ? | 1 Yes | 6 No |
how we can find sieve #4 is 4.75mm?
How do you determine or evaluate success?
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
what is the difference between lap length & development length of reinforcement steel bars
1 Answers APGenco, Consolidated Construction Consortium Limited,
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
what is mean by bulking of sand?
Specific gravity of Cement? Water?
where does the hinged action while designing the strture
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
How many no of bars in a bundle of steel and kgs/bundle. 8 mm, 10mm, 12mm, 16mm, 20mm with both MS and TMT separate.
design mix for M15,M20, M25,M30 please
what is the density of the polythene sheet