How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper

Answers were Sorted based on User's Feedback



How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / sanoj

For calculating the productivity we have to know the
capacity of Excavator.

Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.

Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)

Therefore, net capacity = 1.22*75%= 0.92 Cum.

time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes

Consider 5 minutes rest taken by the operatoer per hour.

Therefore, no of cycles per hour = 55/0.33 = 165

capacity per hour = 165*0.92 = 151.8 Cum/Hour

In similar fashion for dozer and other equipment can be
calculated.

Is This Answer Correct ?    139 Yes 38 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / m subbramanian

Along with above calculation, the distance travelled by the machine should also been taken into account.

Is This Answer Correct ?    44 Yes 6 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / manumitra singh

case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum

Is This Answer Correct ?    29 Yes 5 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / ashebir

calculation for productivity of construction equipment

Is This Answer Correct ?    8 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mickey

There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems

Is This Answer Correct ?    2 Yes 1 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / vinod k

I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.

Is This Answer Correct ?    1 Yes 2 No

How to calculate productivity of construction equipment like excavator, dozer, rock breaker, riper..

Answer / mandar

i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).

Is This Answer Correct ?    1 Yes 6 No

Post New Answer

More Civil Engineering Interview Questions

when will the position neutral axis shifted in beams

3 Answers  


RR masonry rate analysis

0 Answers  


How much cement,sand,bricks and water needed for 1square metre brick work?

0 Answers  


What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?

0 Answers  


In the cement the compound quickest to react with water

2 Answers  






How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?

0 Answers  


how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also

3 Answers  


How much of the strength of concrete comes from post- production curing?

0 Answers   EE Limited, Focus, Lafarge,


what are the differences between shear wall and column

4 Answers   BM, L&T, University of Gondar,


what is the multiplying factor for diffrent types of pcc/rcc ratios?

2 Answers   L&T,


why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?

2 Answers  


What is the consumption of Brick in one meter cube both 6inch & 4inch thick

4 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)