How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answers were Sorted based on User's Feedback
For calculating the productivity we have to know the
capacity of Excavator.
Let me assume the capacity of the Volvo 210 excavator =
1.22 Cum.
Consider the efficiency as 75% (This may be changing based
on the type of material to be excavated)
Therefore, net capacity = 1.22*75%= 0.92 Cum.
time per swing(unload,swing,fill,swing) = 20seconds =>
20/60 = 0.33minutes
Consider 5 minutes rest taken by the operatoer per hour.
Therefore, no of cycles per hour = 55/0.33 = 165
capacity per hour = 165*0.92 = 151.8 Cum/Hour
In similar fashion for dozer and other equipment can be
calculated.
Is This Answer Correct ? | 139 Yes | 38 No |
Answer / m subbramanian
Along with above calculation, the distance travelled by the machine should also been taken into account.
Is This Answer Correct ? | 44 Yes | 6 No |
Answer / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
Is This Answer Correct ? | 29 Yes | 5 No |
Answer / ashebir
calculation for productivity of construction equipment
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / mickey
There is a program can calculate that based on type of soil, distance to dump site etc. MechaNorm by Giant Robot Systems
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / mandar
i believe that the 75% efficiency taken is of operator then the rest taken is not applicable as it is included in the efficiency. As well the material swell factor and the bucket fill factor should also be taken in account plus the machine availability factor should be also accounted (generally less 85 to 95% considered).
Is This Answer Correct ? | 1 Yes | 6 No |
when will the position neutral axis shifted in beams
RR masonry rate analysis
How much cement,sand,bricks and water needed for 1square metre brick work?
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
In the cement the compound quickest to react with water
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also
How much of the strength of concrete comes from post- production curing?
0 Answers EE Limited, Focus, Lafarge,
what are the differences between shear wall and column
4 Answers BM, L&T, University of Gondar,
what is the multiplying factor for diffrent types of pcc/rcc ratios?
why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?
What is the consumption of Brick in one meter cube both 6inch & 4inch thick