How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
What is Critical path in Ms-Project ?
Material calculation of cm 1:6 for 1sqm
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
Why Vitrified tile are getting pop up.
What is Architect-Prepared Contract?
What is the difference between a wood shake and wood shingles?
what are the types of design? which type of method is used at what type of design & why?
What are new methods /technologies of pothole patching?
What is OSHA compliance?
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
1m square 20mm plastering how much of water need curing work
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting