How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / vinod k
I think 75% efficiency is correct as excavation of soil itself takes time & depends upon the area where excavation is to be done, if the excavation area is mix of soil & rocks then efficiency will be less & No. of cycles/hr will also come down.
This calculation is for ideal condition.
Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
What are the strongest shapes in building?
how to calculate the strength of rebound hammer test reading in building construction ?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
in design case of structural member best suitrable percentage of steel limit is what
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
rate analysis hiring of generator 62.5 KVA
What is the Roll of Water Bonding under VDF road?
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
how to caluclate sienerge qty in construction in ap
Critical Path Method is...
water leak detection system question & answer
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
How cracks in concrete can be avoided?