How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
| Is This Answer Correct ? | 29 Yes | 5 No |
Post New Answer View All Answers
Define What is a kip?
How to calculate Volume of Wet cement concrete for a specific grade?
How much time Required for PPR pipe network testing
Explain what is progress payment?
Define mirror?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
Which percentage of carpet area use in plot area of office building.
What is the Unit weight of coarse sand (F.M- 2.20) ?????
why +1 to be followed for calculating the no of bars in BBS. Please explain
What is the Roll of Water Bonding under VDF road?
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
How can we make a hole in a solid rectangle using solidsworks?
how to do sudoko puzaals?
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?