How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
Is This Answer Correct ? | 29 Yes | 5 No |
Post New Answer View All Answers
what course did you consider thinking before you enrolled in college?
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
How many litres of water used for curing of 1000sqft of slav
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
How good are the Weinerberger Porotherm bricks that are being used in construction in Chennai, India. Its being used in non load bearing walls and has a compressive strength greater that 35 kg/cm^2 and a density of approx.694 - 783 kg/m3.
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
what are the duties of Site Engineer in work site?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
Minimum concrete cover in slabs, columns, beams, foundation and other st?
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
What is the yield of 100 litres of water and 10 kg of cement in grout mix?