How to calculate productivity of construction equipment
like excavator, dozer, rock breaker, riper
Answer Posted / manumitra singh
case-1 say komatsu 450 is used
1)bucket capacity-2.4 cum
2)ideal output=load per cycle*no. of cycle/hour
=2.4*100 (considering 35 second cycle say)
=240 cum
3) apply correction factors
a)excavator correction=0.8(if area is not a trench exactly bucket size in which case it is1
b)load factor=0.8(if load has to be dumped in tippers and not kept aside)
c)soil factor=0.67 in case of hard digging and0 .85 in medium digging
d)swing factor=1.07 for 75degree and 0.71 in case of 180 degree.
e)performance efficiency=0.83 if 50 minutes work is done in one hour.
4)corrected output=ideal ouput*a*b*c*d*e
ex: corrected output=240*0.8*0.8*.67*1.07*0.83=91.7 cum
| Is This Answer Correct ? | 29 Yes | 5 No |
Post New Answer View All Answers
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
What is c.g.i sheet which used for roof??
Spider cracks occur in beam bottom due to––
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
Coverage of 25mm.thick ratio of 1:4 cement mortar?
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
significance of specific surface area of particles?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
What is made from large rocks, which protects the base of cliffs?
In cement concrete how to check a quality of material also proportion of material at site ?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
What is the Unit weight of coarse sand (F.M- 2.20) ?????
How do you calculate the power of a centrifugal pump?