Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How much binding wire is required for one tone reinforcement ?

Answers were Sorted based on User's Feedback



How much binding wire is required for one tone reinforcement ?..

Answer / shekhar kundena

8 to10 kg for 1MT of reinforcements depend on structural design.

Is This Answer Correct ?    1 Yes 0 No

How much binding wire is required for one tone reinforcement ?..

Answer / mohammed aijaz hussain, modi b

Generally 4.5 kg to 5 kg of binding wire is consumed for
binding 1 Metric Tonne of steel and for Columns 1.5 kg is
consumed.

Is This Answer Correct ?    12 Yes 12 No

How much binding wire is required for one tone reinforcement ?..

Answer / vikash sharma

one ton m.s tmt bars using bending wire quantity's "12.5kgs"

Is This Answer Correct ?    0 Yes 0 No

How much binding wire is required for one tone reinforcement ?..

Answer / bilal khan

As per standard knowledge in all over the world we use in 1 ton 10kgwire only.

Is This Answer Correct ?    0 Yes 0 No

How much binding wire is required for one tone reinforcement ?..

Answer / simhachalam

One MT Steel is required 9- 13 kg of binding wire

Is This Answer Correct ?    0 Yes 0 No

How much binding wire is required for one tone reinforcement ?..

Answer / ananthbathmanaban

approximately 100 kg of steel required 1 kg of binding wire is required...so for one tone 10 kg of binding wire is required....

Is This Answer Correct ?    1 Yes 2 No

How much binding wire is required for one tone reinforcement ?..

Answer / neeraj kumar

go through with relevent is codes and cpwd specification,
normally it is 7kg per tonne in all the dias and all
locations.

Is This Answer Correct ?    0 Yes 1 No

How much binding wire is required for one tone reinforcement ?..

Answer / partha pratim panja

As per Joglaker (Quantity Surveyor Book) it is mentioned as 
for every quintal of steel reinforcement ( 1 quintal = 
100kg) 0.9 to 1.3kg of binding wire is required




for 100kg of steel reinforcement = 0.9 to 1.0kg of binding 
wire (18 swg)




for 1 tonne (1000kg) = 9 to 1 kg binding wire will be 
required 

Is This Answer Correct ?    0 Yes 1 No

How much binding wire is required for one tone reinforcement ?..

Answer / deepak n.baviskar

8to10 percent of total steel

Is This Answer Correct ?    7 Yes 13 No

How much binding wire is required for one tone reinforcement ?..

Answer / shyam sundar mondal

it depend on dia of bar 8mm to12 mm dia road 6-8 kg /t
and 16-25 mm dia of bar 2.5 - 3 kg/t

Is This Answer Correct ?    0 Yes 6 No

Post New Answer

More Civil Engineering Interview Questions

what is the average steel consumption in multy storey building as a residential and commercial?

6 Answers  


Brick size ? & 1 square feet brick work for use brick

1 Answers   Ashoka Electricals,


What will be weight of 0.5mm GI sheet per sq.ft?

1 Answers  


what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.

0 Answers  


How to calculate unit conversion area

0 Answers  


about 200 cubic mtr

0 Answers  


I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help

0 Answers  


How many types of grades in concrete mixing

6 Answers   White Horse Ventures,


when we select buildup beam

1 Answers  


What is the release of lien?

0 Answers  


What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.

0 Answers   MTC,


1) what do you mean by rolling margin of steel ? 2)pls. tell the cut length formula of stirrups as per IS codes(take out cut length for a beam of 600*300mm with 40mm cover all sides)? 3)what is the multiplying factor of painting for sand faced plaster? 4)if your footing is of size1.9*1.6m . what quantity of length and width you will excavate means what extra margins you will allow as per IS codes in billing?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)