Please tell me how many bricks needed for 4.5" bricks per
m3(how to calculate this also), and outurn of mason. Thanks.
Answers were Sorted based on User's Feedback
Answer / haris iqbal
frist calculate total volume of your brick work
VOLUME OF TOTAL BRICK WORK= L*B*H
NO OF BRICKS = total volume of your brick work * 13.5(one
cubic feet of work requried 13.5 bricks including mortor)
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / santosh singh
you calculate total volume of brick work = L X B X H
L= LENGTH
B= BREADTH
H= HEIGHT
THEN CALCULATE VOLUME OF ONE BRICK WHATEVER MAY BE THE SIZE
OF YOUR BRICK= L X B X H
NUMBER OF BRICKS = TOTAL VOLUME OFBRICKWORK / VOLUME OF ONE
BRICK
Is This Answer Correct ? | 8 Yes | 8 No |
Answer / md.hedayetullah
Firstly decide brick size=L X B X H=.23mm X.115mm X .075 mm
Number are brick in use=1/.23*.115*.075=504.09 bricks
Less two percent of cement mortar=504.09*2/100=10.08
Actual use nos of brick in 1cum=504.09-10.08=494 nos
Is This Answer Correct ? | 1 Yes | 1 No |
What is the difference between compressive strength and crushing strength?
32mm bar column lapping we use welding binding what is dimension of welding as per stander code?
Wat is meant by Aecron brick?
how to design and calculate materail quantity for concrete speedbreaker ?
What is the rate of earthwork excavation?
what is the detention period for oxidation ponds
01m3 cement mortar in cement qty in kg
What is the spacing of chairs in reinforcement steel.If it is written in IS 456:2000 then tell me the page number.
Cement , sand , concrete ration in M30 Grade
in railway engineering, what are the types of guages? what is its size,length & thickness?
I need to know the productivity of meason/labour/barbender/carpenter while doing work like Shuttering, reinforcement steel, brick work, earth work?
In structural steel work what should be the wastage percentage considered to order the material( 200x200x5mm box section) in standard available sizes in India i.e. 6 mtrs?