Answer / shyam.bh
It is a lengthy & detailed process for rate analysis of
equipment.
It is done by the CWC (Capital cost & Wages of Crew) guidelines.
Hourly charges of 62.50 KVA DG
basic cost = 4,00,000.00
add transportation & insurance charge = 32,000.00
Other taxes = 12000.00
Book value of machinary = 4,44,000.00
Rated life = 08 yrs
Rated life in hours = 20,000hrs
Yearly depreciation of the equipment = 49950.00 (cwc
guideline)
hourly depreciation = 20.00 -----A
Interest on capital investment/hr = 16.00 -----B
Repair & maintanance@120% = 24.00 -----C
Fuel charges for operation = 0.026*62.50/0.746*3.04*35
= 232.00
Oil & lubricants @ 25% of above = 58.00
sundries @ 10% of repair charge = 2.00
Total fuel charges = 292.00 ----D
Labour charges
rated life / month = 12000/144 = 166.67 hr/month
regular worker
operator = 8,000.00x0.80 = 6,400.00
mechanic = 10,000.00x0.125 = 1250.00
Total L/C = 7650.00----a
Casual worker watchman = 3000x0.125 = 375.00 ----b
Total L/C = 8025.00
Add hidden charges @ 80% on 'a'& 55% on 'b' =6326.25
Total L/C = 14351.25
Hourly L/c = 86.10 ----E
therefore the hourly charges of a set 62.50KVA
= A+B+C+D+E = 438.20 Rs
| Is This Answer Correct ? | 10 Yes | 0 No |
what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (cement:sand:aggr) ?
What is the difference between Grade I, II and III of GSB?
What is the full form of BHEL? A) Bharat hydroelectricity Limited B) Bharat Heavy Electronics Limited C) Bharat Heavy Electricals Limited D) Bharat Heavy Enterprises Limited
1. why steel used in concrete
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
What is Critical path in Ms-Project ?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
what is the formula for calculating volume of isolated footing? i am not asking for the sloped footing, i am asking for normal rectangle isolated footing, pls add diagram or linkof diagram with answere
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
0 Answers Gammon, Rajiv Gandhi University of Knowledge Technologies RGUKT,
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)