Answer / shyam.bh
It is a lengthy & detailed process for rate analysis of
equipment.
It is done by the CWC (Capital cost & Wages of Crew) guidelines.
Hourly charges of 62.50 KVA DG
basic cost = 4,00,000.00
add transportation & insurance charge = 32,000.00
Other taxes = 12000.00
Book value of machinary = 4,44,000.00
Rated life = 08 yrs
Rated life in hours = 20,000hrs
Yearly depreciation of the equipment = 49950.00 (cwc
guideline)
hourly depreciation = 20.00 -----A
Interest on capital investment/hr = 16.00 -----B
Repair & maintanance@120% = 24.00 -----C
Fuel charges for operation = 0.026*62.50/0.746*3.04*35
= 232.00
Oil & lubricants @ 25% of above = 58.00
sundries @ 10% of repair charge = 2.00
Total fuel charges = 292.00 ----D
Labour charges
rated life / month = 12000/144 = 166.67 hr/month
regular worker
operator = 8,000.00x0.80 = 6,400.00
mechanic = 10,000.00x0.125 = 1250.00
Total L/C = 7650.00----a
Casual worker watchman = 3000x0.125 = 375.00 ----b
Total L/C = 8025.00
Add hidden charges @ 80% on 'a'& 55% on 'b' =6326.25
Total L/C = 14351.25
Hourly L/c = 86.10 ----E
therefore the hourly charges of a set 62.50KVA
= A+B+C+D+E = 438.20 Rs
Is This Answer Correct ? | 10 Yes | 0 No |
Define What is the meaning of a blue land surveyors flag?
Who designed the city of washington dc?
how can i calculate pcc and rcc cu.mtr rate? specify labor and material cost should be diff
What is the minimum size of the particles of silt soil?
how much nails used in 1 sq m shuttering
16 Answers L&T, Pearls, Simplex,
U are a civil engineering student?why do u want to enter into IT industry
What is the difference between Fe 500, Fe 500 D and Fe 515.
Name the standard sand for concrete tests
Clay and silt content in a good brick earth must be at least
Which is stronger solid steel rod or hollow steel pipe?
what is called fck
what is cement mortar cube size and strength in 3days, 7days and 28days