how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
| Is This Answer Correct ? | 19 Yes | 8 No |
Answer / ratheesh
cement = 7.5 kg
sand = .0076 m3
Aggrigate = .015 m3
| Is This Answer Correct ? | 16 Yes | 9 No |
Answer / bharathi
cement - 8.22 Kg
Sand - 0.428 m3
20mm BM- 0.856 m3
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / arunkumar
cement = 3 kg
sand = 0.75 band
20mm metal =1 band
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / darshandachchu@gmail.com
cement=403.5kg
fa=.42cum
ca=.84 cum
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / r.suresh
cement= 11kg
sand = .012cuft
aggregate=.024cuft
| Is This Answer Correct ? | 9 Yes | 11 No |
Answer / n.rajeev
sand = .012cft
coarse aggregate = .024cft
cement = 17.28 kg
| Is This Answer Correct ? | 6 Yes | 8 No |
Answer / v.purushotham
Coarse aggregate: 0.96 cu.ft
sand : 0.48 cu.ft
Cement : 13.06 cu.ft
| Is This Answer Correct ? | 1 Yes | 3 No |
ratio 1:4:8: for pcc. area 1008 cft. thickness 6' what is the quantity we need
coarse sand has a fineness modulus in range of
What is tha cross secional area of cover block
what is the difference between np2 and np3 concrete mix
0 Answers Sri Matha Constructions,
how much shuttering oil required for 100 sqm shuttering?
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
clean earthing and dirty earthing
1 Answers CSCEC-China State Construction Engineering Corporation,
What is the exact meaning for under & over reinforced beams & when they have to used..
11 Answers Gammon, L&T, MEIL,
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
FOR concrete structure curing is important for hydration process,curing component is good for the concrete if W/C ratio is more than .38
Why the height of the bridges over the river are very low?
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)