how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
| Is This Answer Correct ? | 19 Yes | 8 No |
Answer / ratheesh
cement = 7.5 kg
sand = .0076 m3
Aggrigate = .015 m3
| Is This Answer Correct ? | 16 Yes | 9 No |
Answer / bharathi
cement - 8.22 Kg
Sand - 0.428 m3
20mm BM- 0.856 m3
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / arunkumar
cement = 3 kg
sand = 0.75 band
20mm metal =1 band
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / darshandachchu@gmail.com
cement=403.5kg
fa=.42cum
ca=.84 cum
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / r.suresh
cement= 11kg
sand = .012cuft
aggregate=.024cuft
| Is This Answer Correct ? | 9 Yes | 11 No |
Answer / n.rajeev
sand = .012cft
coarse aggregate = .024cft
cement = 17.28 kg
| Is This Answer Correct ? | 6 Yes | 8 No |
Answer / v.purushotham
Coarse aggregate: 0.96 cu.ft
sand : 0.48 cu.ft
Cement : 13.06 cu.ft
| Is This Answer Correct ? | 1 Yes | 3 No |
about higyway engineering
How do you calculate the mix ratio of concrete i.e. what is the cement:sand:agrugate ratio in 20Mpa, 21Mpa, 22Mpa etc...
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Can anyone give me the thumb rule for calculating the time required for construction based on quantity of concrete, Reinforcement, shuttering, etc
Name the standard sand for concrete tests
How can we compact the soil on slope portion? What is the Grade II of Stone Metal?What type tests carried out on BBM road?
Is there any alternate for plastering
in BUILT UP AREA BASIS WHAT IS RATIO OF CONCRTE & STEEL RATIO MAY BE CONCIDER IN PER SQFT QTY
Describe the role of independent Quantity surveyor?
how much water you will add to the mix, for making 1 m3 of concrete to achieve strength of mix 20N/mm2 at 28 days.
what is means of M50,M20,M15 like this please tell me ?
How can calculate the number of bricks.....? Give me answer hurry uppppppppp
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)