how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answer Posted / mohammed aijaz hussain
Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
| Is This Answer Correct ? | 19 Yes | 8 No |
Post New Answer View All Answers
Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?
Explain what is alternate bid?
how much need sand and cement for 1 cft roof construction?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
How to calculate steel for beam slab and column
how to absorb to site basic corrections? which are the important correction?
What is the difference between built area and super built up area?
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
Define What is rigging?
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
What are the RISKS during the project construction?
Which brick is best for construction ,either fly ash or AAC BLOCKS
WHAT IS YOUR EXPECTED SALARY?
What goals do you have in your career?