How to calculate the amount of cement & sand required for
plastering work with ratio 1:4 please give me an answer with
detailed step.
Answers were Sorted based on User's Feedback
Answer / rajarshi basu
Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:
1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags
>> 11 bags(say)
Cement used =11 x 50= 550 kg
2)Sand required= [1.92 x (4/5)]= 1.536 cu. m
Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Hope u have understood!!!!
Is This Answer Correct ? | 482 Yes | 42 No |
Answer / shalini mishra
Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:
1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags
>> 11 bags(say)
Cement used =11 x 50= 550 kg
2)Sand required= [1.92 x (4/5)]= 1.536 cu. m
Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Is This Answer Correct ? | 70 Yes | 9 No |
Answer / matrix civil & structural
THE METHOD GIVEN BY Mr.BASU IS SEEMS TO BE APPROPRIATE TO ESTIMATE THE QUANTITY OF CEMENT AND SAND IN PLASTERING.
Is This Answer Correct ? | 66 Yes | 21 No |
Answer / baldeo m. sarwe
Yes this formula is near abovet is correct
Is This Answer Correct ? | 27 Yes | 10 No |
Answer / xxx
this answer is write but their is not mention that weight of sand...
Is This Answer Correct ? | 4 Yes | 4 No |
Answer / kanheya lal
footing by structures weight formula in steel dia for load
Is This Answer Correct ? | 1 Yes | 1 No |
What is Refuse Area In High Rise Building ?
Can we use 16mm dia bar in place of 12mm dia bar in COLUMNS? (if given dia bar is not available on site)
What is the cemnent ratio
what is the IS code no. for concrete wastage?
What are the advantages of cad?
Can inverted beams used in pipes during construction?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
what is meant by civil engineer?
What should be the required steel in column, beam and slab
what is the difference between np2 and np3 concrete mix
0 Answers Sri Matha Constructions,
How to calculate the amount of cement & sand required for plastering work with ratio 1:4 please give me an answer with detailed step.
6 Answers DSR Management, Simplex,
What is the ratio of cement ,sand, and aggregate to be used in M20 grade of concrete when excavating 200 x 200 x 200 mm of sand from soil