How to calculate the amount of cement & sand required for
plastering work with ratio 1:4 please give me an answer with
detailed step.
Answer Posted / rajarshi basu
Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:
1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags
>> 11 bags(say)
Cement used =11 x 50= 550 kg
2)Sand required= [1.92 x (4/5)]= 1.536 cu. m
Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Hope u have understood!!!!
Is This Answer Correct ? | 482 Yes | 42 No |
Post New Answer View All Answers
what is your role of in previous company as a construction manager
How much material will consume for following specification water tank (9*7.5*6 feet)?
How to make a c++ program that converts any base to base 10?
For fine aggregate which is most suitable River sand or crusher sand & why ?
cause of cylinder test failure
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
undistributed samples are obtained by
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
how do you stabilize a waterlogged area in road construction
what is project?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
In case if concrete box girder bridges how is the number of cells determined?
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
what is the maximum number of course that can be laid according to IS code and the max height.
How do You Maintain a structure after getting cube test of low strength.