Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the amount of cement & sand required for
plastering work with ratio 1:4 please give me an answer with
detailed step.

Answer Posted / shalini mishra

Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.

Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]

Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:

1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags

>> 11 bags(say)
Cement used =11 x 50= 550 kg

2)Sand required= [1.92 x (4/5)]= 1.536 cu. m

Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.

One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]

Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347

Is This Answer Correct ?    70 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.

2083


how much used soil in 1 brick of standard size?

2029


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2044


WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?

2419


what is difference between fluidity and workability also how palsticizer works

7409


what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15

2960


In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?

1042


a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.

2327


What are the advantages and disadvantages of using plastic and timber fenders?

1118


how many material required for brickbat water proofing of toilets.

1984


How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy

2005


1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?

6553


five benefits of using standard terminology in the measurement process

3400


Which is the latest version of solidsworks?

1219


what is civil enginnering & what you need of this course?

2207