how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answers were Sorted based on User's Feedback
Answer / sateesh patil
If you Consider M25 Grade Concrete Nominal mix Design is
1:1:2(1 Cement:1 Sand:2 Aggregates)
1+1+2=5
Volume of Dry Mix=1.5% X Volume of wet mix
If you Consider 1 Cum Concrete
Cement=1/5X1.5(1)=0.3 Cum(1 Bag of Cement=50 Kgs=1.235
Cft=0.035 Cum)
Then 0.3 /0.035=8.57 bags=428 kgs
Sand=1/5X1.5(1)=0.3 Cum=10.584 Cft
Aggregates=2/5X1.5(1)=06 Cum=21.168 Cft
| Is This Answer Correct ? | 53 Yes | 172 No |
How to calculate carrying capacity of the existing water supply trunkmain
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
what is the average steel consumption in multy storey building as a residential and commercial?
VAT and CST ? Which benefits for buyer ? Why benefits?
While casting slab at what length slab casting should be stop
explain the difference between short column and long column
What are the structural steel & where they are used
what is the weight of 12mm aggregates?
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
Which foundation is stronger, Pile or Standard?
What is the largest concrete dam in the world?
WHAT IS FLOOR AREA RATIO? Y IS IT NECESSARY? HOW TO CALCULATE IT?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)