Answer / saiprasad malandkar
Deshuttering time as per IS-456-2000
IS 456-2000,clause-11.3.
Type of Formwork minimum period
a) Vertical formwork to columns, walls, beam 16-24 h
b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days
c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days
d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days
e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days
Is This Answer Correct ? | 49 Yes | 0 No |
Answer / santhosh kumar
basically deshuttering of slab is in depend up on the mix
propotion of the concrete.and achived strength more than
75%.
like m15 is needed for deshuttering period is 21 days
we are using m20,for slabs need 14 days is enough.
in beams we are using m20 and above 10 ~14 days are
applicable in practcial.
for using post tension in the slab we are using m35
concrete in slabs it is deshutttered 7 ~ 8 days.(when the
portion is after stressed)
to calculate the concrete strength in lab take 3 cube of
concrete and tested in lab 3 cube average strength is
needed 75%.
Is This Answer Correct ? | 59 Yes | 12 No |
Answer / nikunj faldu
yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.
one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.
Is This Answer Correct ? | 26 Yes | 4 No |
Answer / harbans singh
It is also depends on whether in cold deshuttering required
more time.
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / benny joseph
Solid slab 30cm thick x 1000 m2 deshuttering shall be how many days of after casting ( slab mix opc 380kg) 7days curing
Is This Answer Correct ? | 0 Yes | 1 No |
I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.
Definition of plinth beam & Uses.
what will be price of 1:2:4pcc per kg?
0 Answers Intellect Engineers,
How to find out slope footing concrete
0 Answers Ekta World, Punj Lloyd Ltd,
hi... how to find reaction in continous beam 4 different span ?
The relation between cube strength & cylinder strength because––
steam curing is not used in which cement
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
pls tell me , what is the water content
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
What is mean by ITP in a construction project
Is there any alternate for plastering