what is periode of deshuttering for different area of slab
Answers were Sorted based on User's Feedback
Answer / saiprasad malandkar
Deshuttering time as per IS-456-2000
IS 456-2000,clause-11.3.
Type of Formwork minimum period
a) Vertical formwork to columns, walls, beam 16-24 h
b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days
c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days
d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days
e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days
| Is This Answer Correct ? | 49 Yes | 0 No |
Answer / santhosh kumar
basically deshuttering of slab is in depend up on the mix
propotion of the concrete.and achived strength more than
75%.
like m15 is needed for deshuttering period is 21 days
we are using m20,for slabs need 14 days is enough.
in beams we are using m20 and above 10 ~14 days are
applicable in practcial.
for using post tension in the slab we are using m35
concrete in slabs it is deshutttered 7 ~ 8 days.(when the
portion is after stressed)
to calculate the concrete strength in lab take 3 cube of
concrete and tested in lab 3 cube average strength is
needed 75%.
| Is This Answer Correct ? | 59 Yes | 12 No |
Answer / nikunj faldu
yas, santhosh kumar statment is right, but that depend up
on span of slab also, bcos. the dead load of slab is bigest
fector efecting on deshuttering.
than second, almost people remove shuttering below the slab
and beam bottom are stay long time, unother give a support
on bottom and remove shutter, that's all right.
one more sugetion is if that wall shuttering so, u must be
remove after 24 to 36 hours.
| Is This Answer Correct ? | 26 Yes | 4 No |
Answer / harbans singh
It is also depends on whether in cold deshuttering required
more time.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / benny joseph
Solid slab 30cm thick x 1000 m2 deshuttering shall be how many days of after casting ( slab mix opc 380kg) 7days curing
| Is This Answer Correct ? | 0 Yes | 1 No |
What is green building?
What is the strength of normal brick in india
Meaning of m20 and m200 concrete
10 Answers WBPSC West Bengal Public Service Commission,
what is the ingredient value of 40mm and 20mm aggregates?
0 Answers Nexus Technologies, Power Grid,
what is anchor bar??
what are the Task work of different labour.?
natucher of concrete &type of concrete?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
What are the Types Of DPC and its Thickness used?
what is the basic idea of well sinking????
1 Answers Quality Water Management Systems, Simplex, Sobha Developers,
Can anyone tell me the salary and job profile of transportation engineers/transport engineer?
what is the minimum cement content for rcc as per is code
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)