what is periode of deshuttering for different area of slab
Answer Posted / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is meaning of FREE STANDING STAIRCASE ?
how much of the strength comes from post-production curing
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
How we calculate the service time of buildings
Define What is rigging?
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
How much area will be covered in 1 litre of Velvet touch paint in normal wall condition
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
what is the anchorage length of reinforcement.
How much time Required for PPR pipe network testing
please briefly explain calculating or estimating steel quantity for a RCC column?
how to nfind out the specific gravity of sand.aggregate,water please help...
60-70 grade of Bitumen is VG-30 ?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
Differentiate first angle & third angle projection?