what is periode of deshuttering for different area of slab
Answer Posted / nitin patil
What santosh kumar given answer is correct.but sometimes it is observed that for M20 grade slab deshuttering is done in 7-8 days.it depends on the material used also.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what is w/c ratio in dry lean concrete for m10 mix design
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
What is Architect-Prepared Contract?
can i get civil engineering test papers.......?????
what is the max. area can we apply the plate load test ?
how many type of admixtures for water stored structure?
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
how to find quantity of concrete in PCC M15
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
what are the code used for residental building?
What is the difference between EPC,DBOOT and BOOT.
What is factor not to be taken in consideration in mix design?
How did street originate in the plumbing term street ell?
What are your goals?
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?