what is periode of deshuttering for different area of slab
Answer Posted / saiprasad malandkar
Deshuttering time as per IS-456-2000
IS 456-2000,clause-11.3.
Type of Formwork minimum period
a) Vertical formwork to columns, walls, beam 16-24 h
b) Soffitformwork to slabs (Props to berefixed immediately afterremoval of formwork) 3 days
c) Soffitformwork to beams (Propsto be refixed immediately afterremoval of formwork) 7 days
d) Propsto slabs: 1) Spanning up to 4.5 m 7 days
2) Spanning over4.Sm 14days
e) Props to beams and arches: 1) Spanning up to 6 m 14 days
2) Spanning over6 m 21 days
| Is This Answer Correct ? | 49 Yes | 0 No |
Post New Answer View All Answers
Form where IS456 is adopted in 1978?
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?
specifications of fe500 steel
may i know the detailed description of cutting length
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
What are the types of slump?
What will you do if you encounter problems like accidents?
Why is concrete cube test carried out?
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
What are the uses of layer?
what is cross hair cursor?
how much tempareture are required to make liquid state of pid leed
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8
How does a traffic light signal work ?