Answer / jinchandra
It is ATP CHECK,
WHICH IS CARRIED OUT FOR FOLLOWING,
1]MATERIAL
2]CAPACITY
3]PRT
It check the material available in warehouse stock,to
fulfill the planned indpendant requirements.
if not,it checks the missing parts,and evaluates,
Similarly it checks the capacity available.
Is This Answer Correct ? | 9 Yes | 0 No |
Answer / venu
Availability check is used to check whether a product can
be confirmed in a sales order, based on the fact that
enough stock is available or can be produced or purchased
on time.
Is This Answer Correct ? | 6 Yes | 1 No |
Answer / nitin thapliyal
This field has two uses:
1. Specifies whether and how the system checks availability
and generates requirements for materials planning.
2. In Flexible Planning, defines - together with the
checking rule - the different MRP elements that make up
this key figure. The sum of these elements gives the key
figure
It can be done as follows
01 Daily requirements
02 Individ.requirements
CH Batches
KP No check
Is This Answer Correct ? | 3 Yes | 2 No |
What is availability check? How can it be done?
types of mrp?
What are mandatory fields for PP configuration
Mention how mrp (material requirement planning) types are classified?
In cost controlling information system mention the fields that are listed in the list screen of the report?
I have having 14 years manufacturing experence & 6 years in SAP-PP/QM.Was a core member during implementation.Now I want to work as Functional Consultant in SAP-PP/QM.What should I do for getting the jobs.
What is recursive BOM
We are trying to create purchase requisition from mrp run. We have material, info record, source list, demand in place. Mrp is always creating plan order. Why?
What is the uses of production scheduling profile and what the configure have you done current project
0 Answers Cognizant, Patanjali Ayurved,
How system calculate the actual cost?
Hi Sir, Please guide me i am an BSc computer science graduate with MBA in Agri business having 3 years of exp in Food Processing Industry in Production please advice shall i persue with SAP PP? Many thanks
Difference between NETCH, NETPL and NEUPL.