how we can calculate the transformer size.

Answers were Sorted based on User's Feedback



how we can calculate the transformer size...

Answer / pravin sathalpara

it is depend upon the load beacause trasformer equistion
is
kva=VICOS
SO,OUR VOLTAGE AND CURRENT(LOAD) IS DECIDE FIRST

Is This Answer Correct ?    0 Yes 0 No

how we can calculate the transformer size...

Answer / bhagaban barik

KW=KVA*P.f
i.e- KVA=KW/p.f

It also depends on Utilisation factor & maintenance factor

we have to consider 30% margin for future expansion

Is This Answer Correct ?    0 Yes 0 No

how we can calculate the transformer size...

Answer / papuraj

Its purely depends upon your maximum demand nothing else.For an example if you have the connected load is 700kva and maximum demand is only 350kva, hence we could select 500kva transformer to be with 20% future additional load.

Is This Answer Correct ?    0 Yes 0 No

how we can calculate the transformer size...

Answer / rajani

SIZE OF TRANSFORMER DEPENDS THE FOLLOWING


CONNECTED LOAD EX:2500KVA
MAXIMUM DEMAND EX:1500KVA
STARTING LOAD EX: 500KVA
LOAD FACTOR EX:0.9
FUTURE LOADS EX: 20% EXTRA TO MAXIMUMDEMAND

SO TRANSFORMER SIZE IS (1500+500+20%(1500))*0.9=2070KVA
SO 2200KVA TRANSFORMER IS ADEQUATE FOR MAX DEMAND OF
1500KVA LOAD.

Is This Answer Correct ?    19 Yes 20 No

how we can calculate the transformer size...

Answer / abhishek ranjan

transmer size can be calculated according to load.
its also depend on the material used.
if we use HRS in the place of CRGOS then its size will increse

Is This Answer Correct ?    12 Yes 20 No

how we can calculate the transformer size...

Answer / mitul

Transformer size ,we can consider what is the maximum load and for future expansion 25% shall be considered

Is This Answer Correct ?    1 Yes 9 No

how we can calculate the transformer size...

Answer / v v s reddy

Check the following conitions

1. Rating of transformer is sufficient to totao load
2. Thermal loading on the transformer during motor starting
3.Voltage available at motor terminal during motor starting
4.Voltage available at bus during motor starting

Is This Answer Correct ?    7 Yes 16 No

how we can calculate the transformer size...

Answer / vladimir tutulaku

WE HAVE A OLD TRANSFORMER WITHOUT TARGET
HOW WE CAN DECIDE THE POWER OF TRANSFORMER

Is This Answer Correct ?    4 Yes 13 No

how we can calculate the transformer size...

Answer / u.chandarasekar

It is Very Very Simple take one Measurment Tape

Is This Answer Correct ?    1 Yes 10 No

how we can calculate the transformer size...

Answer / rajesh

Transformer size is decided based on the following factor.
--> Load details
--> Load factor
--> coincidence factor
--> BKW value
--> Other than this it required power factor of the loads.

By using the following formulas we can calculate the
kva rating.
cosф * KW = KVAr

(KVA)2 =( KW)2 +( KVAr)2

Is This Answer Correct ?    8 Yes 24 No

Post New Answer

More Electrical Engineering Interview Questions

What is the difference between a 3 winding and 2 winding Potential Transformer

0 Answers   Engineers India,


what will happen to give a dc supply in ac motor?

2 Answers   ABC, Indian Navy,


why constant voltage transformer should be start without load? and if started then what will happen?

0 Answers  


what is the working of air drayar

1 Answers  


internally connection of photvoltic module

0 Answers  






What is meant by operating sequence of VCB : 0–0.3sec.–CO– 3min.-CO

2 Answers  


how do we calculate length of starting time and repeated starting of a direct online starter?

0 Answers  


how electricity is generated through electeic generator ?

1 Answers  


why generator is star connected ?

3 Answers   Voltech,


Importance of fault current in power transformers and how to monitor the same? How is it different from winding temperature?

0 Answers   Impulse,


We have a 12MW power plant & we inject 5-6MW power to Orissa GRID. For this we have a 33KV/11KV switch yard having 12.5MVA power transformer. Some times we draw power during emergency. It is observed that during Export or Import for load less than 500Kw the power factor is decreasing to 0.3 . This is happening only during export or import. During island condition TG power factor OK.Our capacitor bank is provided with our Power plant auxilliary load. Please suggest how I can we improve our power factor during low load (GRID).

3 Answers  


What is purpose of APFC panel?

7 Answers   Techno Electric and Engineering,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)