Answer / n amarender reddy
Negative Time Recording method means the only time data
entered into the system which represents a deviation from an
employee's planned work schedule. It means it will
automatically takes the planned work schedule time data with
out entering and you need to only enter the deviation to the
planned work schedules.
Ex:Absences, Overtime, Substitutions.
Positive Time Recording method means the time data to be
entered into system includes the deviations from the planned
work schedules as well as the attendence(actual) times
during which the employee works for the organization.
Ex: Deviations(Absences, Overtime, Substitutions) + All
Attendances
Is This Answer Correct ? | 22 Yes | 2 No |
Answer / rajesh kumar
In negative time recording, only deviations in planned
working time is taken into consideration. It is considered
that rest of the time employee works as per the planned
working time.
In positive time recording actual duration the employ
worked will only be considered.
Is This Answer Correct ? | 13 Yes | 1 No |
Answer / kulvinder obhan
With a Positive Time Status, you must enter all information
for the employee to be paid. With Negative Time Status,
the system generates all the regular information, thus, the
entry clerk need only enter the exceptions to the employees
regular schedule.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / deepak
positive time management means recording time data according to work schedule.
Negative time management is recorging deviations only.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / bangaramma
I sended this question. And also now i am sending answer
Navya. Are you working any where? These two difference:
Without time evaluation:
TE without clock time mean negative time recording as well
as positive time recording.These two differentiation is
given below.
+Ve TR -ve TR
EMP: Not so strict, not so liberal very liberal
TMS:1 9
Schema:TM04 TM04,TM01
PCR: TMON TMON
Actual duration of work Emp.working according
to planned working
hours
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / manikumar
Hello friends.........
Banagaramma..... i would appreciate if you can explain this
question in a more cleart confused,
the question says...with out time evaluation does that mean
the TMS: 0 (No Time Evaluation).
it would be great if you can contact me on my Email id:
bbv_manikumar@yahoo.co.in
Is This Answer Correct ? | 2 Yes | 4 No |
Answer / krish
any deviation to the planned work schedule is calculated
using negative and Planned work schedule is calculated by
Postive .
Normally most of the company they use both +VE AND _VE time
recording .
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / pallavi
The main difference between the positive and negative time
recording is
In positive the attendances and absesnces are calculated by
the time machine.ie swipe cards.
In negative the administrator has to calculate time
manually.
Is This Answer Correct ? | 5 Yes | 13 No |
How you choose the team?
In tm, if group of employees get 10 days of annual leave, what will be the time evaluation status?
In APP we are making payments on every friday. If client wants to make in between friday is it possible. How it is?
How is a functional area displayed on the adhoc query screen?
What is the use of the pactv feature?
what is the link among organizasion structure and enterprise structure, personnel structure, payscale structure?
what is key or knowledge data structure??? does any one have a format of it for hr???....help needed on early basis....
what are the different posting processes available?
Hi, questions is if an employee working in our company with salary 10000 per month. up to december the salary was given. company has given a hike of 5000 to the employee in the january month 2009 this hike salary to be added from the month september 2008 questions: 1) how many payroll result records will be generated 2) what is for-period & in-period
In supporting project, what are the Tickets generally we come across in payroll, personnel administration and Organizational management?
How is time managment and payroll is integrated?
What is the transaction code for initial applicant data entry?