Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the individuals quantities of cement,sand,and aggregate
having 1:2:4 ratio for 50 cubic meter area.

Answer Posted / palguna

The proportions of
cement-1 ,sand -2 aggregate-4, the sum of total aggregates is 7
the volume of wet cement concrete is 1.54 to 1.57
then the solution is cement = 1x1.57x1440/7= 322.57 kg
(here 1440 is density of cement 
for sand = 2x1.57/7=0.4485 cum
aggregate = 4x1.57/7=0.897 cums

Is This Answer Correct ?    8 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why should appointment store person for project ? what is the benefits for company ?

1106


pls give me ans to ACT formula cube testing porpuse

3070


i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard

2345


What is the procedure of concealed plumbing in toilets?

2346


for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area

2349


what is that one cub metre plaster in cemant and fine sand

2039


what are the layers of the national and heir aprox thickness??

2125


suppose that  156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.

2714


What is difference between combin footing & rapt footing

1905


50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?

1952


Define a polyline?

1231


how to workable concrete cube test M-25 design mix

3458


can i get civil engineering test papers.......?????

2453


What is the difference between shear and tensile strength?

1137


relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2

2980