How to calculate the individuals quantities of cement,sand,and aggregate
having 1:2:4 ratio for 50 cubic meter area.
Answer Posted / palguna
The proportions of
cement-1 ,sand -2 aggregate-4, the sum of total aggregates is 7
the volume of wet cement concrete is 1.54 to 1.57
then the solution is cement = 1x1.57x1440/7= 322.57 kg
(here 1440 is density of cement
for sand = 2x1.57/7=0.4485 cum
aggregate = 4x1.57/7=0.897 cums
| Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
Why should appointment store person for project ? what is the benefits for company ?
pls give me ans to ACT formula cube testing porpuse
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
What is the procedure of concealed plumbing in toilets?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
what is that one cub metre plaster in cemant and fine sand
what are the layers of the national and heir aprox thickness??
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
What is difference between combin footing & rapt footing
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
Define a polyline?
how to workable concrete cube test M-25 design mix
can i get civil engineering test papers.......?????
What is the difference between shear and tensile strength?
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2