How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3
Answers were Sorted based on User's Feedback
Answer / rajarshi basu
Keeping the casting of piling in mind on site,it would be
foolish to answer this kind of question as the concrete used
for casting is RMC where we dont get to know the proportions
of mixes the mix designer has used to design the specified
concrete.
Otherwise it is too simple to calculate from Nominal mix design
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / ameen chouhan
The ratio 1:1 is micro piles and 22bags per cum
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / s.r.shiradhonkar
vol of pile is 0.63 cum
Material required
Metal (0.80 cum/cum of concrete)i.e 0.8*0.61=0.488 cum
Sand (0.40 cum/cum of concrete) i.e 0.4*0.61=0.244 cum
cement(0.40 cum/ per cum), (as cement sand ration mentioned
1:1). cement required= 0.4*.0.61=.244 cum. 1bag of 50 kg
have volume 0.035 cum. there for bags required=0.244/.035=
7 bags.
S.R. Shiradhonkar
Amarawati.
| Is This Answer Correct ? | 6 Yes | 7 No |
Answer / dushyant bansal
For 1:1 Cement sand ratio
total volume of either will be same as the ratio will be
1:1
and Sand will cover about 80% volume hence 0.8*0.61=
0.488cum
and same vol of cement.
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / sjtbehera
8. Volume of pile -.61m³
If you given cum your ratio is 1:1:2 not 1:1
Total ratio=1+1+2 = 4 so cement = .61/4=.1525m³= 4bags
Sand=.1525cum
Agg.=.1525*2=.305m³
| Is This Answer Correct ? | 5 Yes | 20 No |
What ingredients with% found in ppc cement??
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
Describe the term BILL OF QUANTITY (BOQ)?
How calculate the water for 1m3 concrete
Which ratio use for cement selery???
what is the lap length for pile reinforcement cage in water piling
A person becomes tired when ups a stairs because of––
If length is 20 m ,width is 20 m & thickness is 80 mm then how many brass it is?
how much cost of single coat 20mm thick plastering per sqre meter
what is the standard gradient or slope for drainage?
DEFINE M30 GRADE CONCRETE. FROM THIS QUESTION WHAT; "M" & 30?
7 Answers Descon, Northstar Homes,
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)