how much quantity of sand,cement,reqired for 100sqft of wall construction.
And how much quantity required for plastring



how much quantity of sand,cement,reqired for 100sqft of wall construction. And how much quantity r..

Answer / ramadass

Required of cement : 33.48kg
required of sand :133.92kg

Is This Answer Correct ?    5 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

which things consider when the calculate the area of the flat?

2 Answers  


what is the specific gravity of cement .define it and value?

1 Answers  


how to calculate sand, aggregate and cement in m25 concrete?

2 Answers   CCL Products, Western Infrastructure,


What is quantity of Cement and Sand required for the 1 cum brick masonry with 1:6 Ratio cement mortar.

2 Answers   RPP Infra Projects, SIL,


one MT of steel for using how much binding wire required?

5 Answers  






3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.

0 Answers  


design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal

0 Answers  


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

0 Answers  


Please tell me how many bricks needed for 4.5" bricks per m3(how to calculate this also), and outurn of mason. Thanks.

3 Answers  


structural engineering based

4 Answers   HPCL, L&T,


1 cft have 13.5 No of Bricks, can someone help me to answer me for it's mathematically proof?

2 Answers  


in how much square meter of slab we are providing a beam it may be oneway or twoway slab.

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16636)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)