how to calculate sand, aggregate and cement in m25 concrete?
Answers were Sorted based on User's Feedback
Answer / rohit singh
Grade m25= 1:1:2 , sum=1+1+2=4
Dry concretein 1 cum =1. 52
Cement =1. 52/4=. 38*28. 8=10. 94bags cement /cum concrete
Sand=1. 54*1/4=. 38cum
Aggregate=1. 54*2/4=. 76cum
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / narayan rijal
1.52/(1+1+2)*28.81=cement bags
0.41=sand
0.83+aggregate
| Is This Answer Correct ? | 3 Yes | 8 No |
if we make b.b.s then bend correction is taken how much..
what is the difference between rcc pipe (pressure or non- pressure)and rcc hume pipe?
How many 6.5 * 6.5 tiles would i need for a 36-sqaure-foot room?
how many express way in india
in the footings first which reinforcement bar has to be layed as per design criteria.
how many nos of National highway in India.
13 Answers HBC, L&T,
What should be the PH value of water for irrigation purpose
how many lab test on bricks and aggregate write briefly please
how statics is different from dynamics
What Are The Steps Involved In The Concreting Process, Explain?
In beams why we give lap in middle of top bars and at edges in bottom bars???
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)