one MT of steel for using how much binding wire required?

Answers were Sorted based on User's Feedback



one MT of steel for using how much binding wire required?..

Answer / neel

8 kg / MT

Is This Answer Correct ?    19 Yes 3 No

one MT of steel for using how much binding wire required?..

Answer / k t shivashankar

it is mainly based on design
avg we can take it as 5 kgs / tonne

Is This Answer Correct ?    3 Yes 0 No

one MT of steel for using how much binding wire required?..

Answer / neel

8 kg/mt is for normal design. For heavy sructures quantity
may varries

Is This Answer Correct ?    1 Yes 0 No

one MT of steel for using how much binding wire required?..

Answer / mahesh

10 to 13

Is This Answer Correct ?    1 Yes 2 No

one MT of steel for using how much binding wire required?..

Answer / arunachalam subiramani

One MT of steel consumed binding wire 5 kgs

Is This Answer Correct ?    0 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

What is the difference between Wraft and file foundation and where these are used ?

2 Answers  


Can inverted beams used in pipes during construction?

0 Answers  


For what purpose bedding is used under storm water drains, explain?

0 Answers  


What ingredients with% found in ppc cement??

0 Answers  


how to mack bbs

1 Answers  






IS code for Rolling Margin of steel

0 Answers  


1cracks found in brick wall in service building, how to rectify it,with low cost ? how to find propagation of cracks (in depthwise) and arrest on that stage? Is it require to design for Expansion joint in Brick work? if so what is the required distaces?

1 Answers  


is plate load test can be done on cohesive soils for immediate settlements ?

2 Answers   ONGC,


Difference between design mix and nominal mix

2 Answers   Aegis, CCCL, UltraTech,


density of flyash

4 Answers  


why you considers yourself suitable for the post of site engineer

5 Answers   Consultancy, Nalco, Ritspin Synthetics,


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)