How Many Brick in One Cubic Meter.
Answers were Sorted based on User's Feedback
Answer / vikas chauhan
Standard(Actual) size of Modular Brick = 190mm x 90mm x 90mm
Nominal(with mortar) size of Modular Brick = 200mm x 100mm x 100mm
One Cubic Meter Brick work = 1cum = 1m x 1m x 1m = 1000mm x 1000mm x 1000mm
Now if we Divide 1cum Brick Masonary work by one Brick volume then we get number of bricks in 1cum.
So number of bricks in one cubic meter "Brick Masonary Work"= 1cum/1Brick volume = 1000mm*1000mm*1000mm/200mm*100mm*100mm = 500
So number of Bricks in one cubic meter "brick masonary work" = 500 Nos.
| Is This Answer Correct ? | 31 Yes | 2 No |
Answer / komalvgarg
its is taken as 500 Nos. in 1 Cum of brickwork.
But when u measure at site it comes from 430-480 Nos/Cum. due to variable sizes of bricks and mortar thickness.
| Is This Answer Correct ? | 32 Yes | 4 No |
Answer / ahasan syed
the brick size without mortar 19cm x 9cm x 9cm total brick
is 650 nos of 1 cubic mtr
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / subhash
including wastage 500nos
excluding wastage & mortar 460-465nos
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / kanchan
With mortar
no. of bricks per cum= 480nos.
Without mortar
no. of bricks per cum= 500nos.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / ganesh bharsakle
the brick size without morter 19cm x 9cm x 9cm. total brick
is 550 nos of 1 cubik meter.
| Is This Answer Correct ? | 3 Yes | 10 No |
In structural steel work what should be the wastage percentage considered to order the material( 200x200x5mm box section) in standard available sizes in India i.e. 6 mtrs?
In built up area basis what is ratio of concrete
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance
what is bending moment, for simply supported slab ? how do you calculate ?
how sir calculate the slab steel and sir i want to know that how i calculate shutter works payments in cum and the rate is 120 per cum
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
what is the use of bottom reinforcement in Cantilever Beam?
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
If 600mm*200mm*150** size bricks comes 55 piece in one cubic meter then how many 230mm*115mm*75 bricks in one cubic meter
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)