1. Five steps of implementation with full details.
Answer / devarshi shukla
ASAP stands for Accelerated SAP.
Its purpose is to help design SAP implementation in the most efficient manner possible. Its goal is to effectively optimize time, people, quality and other resources, using a proven methodology to implementation.
The Five Phases of Implementation as under:
Phase 1 Project Preparation
Phase 2 Business Blueprint
Phase 3 Realization
Phase 4 Final Preparation
Phase 5 Go-Live and support
Phase-1 initiates with a retrieval of information and resources. It is an important time to assemble the necessary components for the implementation. Some important milestones that need to be accomplished for phase 1 include
- Obtaining senior-level management/stakeholder support
- Identifying clear project objectives
- Architect an efficient decision-making process
- Creating an environment suitable for change and re-engineering
- Building a qualified and capable project team.
Phase 2- Business Blueprint
SAP has defined a business blueprint phase to help extract pertinent information about your company that is necessary for implementation. These blueprints are in the form of questionnaires that are designed to probe for information that uncovers how your company does business. As such, they also serve to document the implementation.
Each business blueprint document essentially outlines your future business processes and business requirements. The kinds of questions asked are germane to the particular business function, as seen in the following sample questions:
1) What information do you capture on a purchase order?
2) What information is required to complete a purchase order?
Phase- 3 - Realization
With the completion of the business in phase 2, "functional" experts are now ready to begin configuring SAP.
The Realization phase is broken in to two parts.
1) Your SAP consulting team helps you configure your baseline system, called the baseline configuration.
2) Your implementation project team fine-tunes that system to meet all your business and process requirements as part of the fine tuning configuration.
The initial configuration completed during the base line configuration is based on the information that you provided in your blueprint document. The remaining approximately 20% of your configuration that was not tackled during the baseline configuration is completed during the fine tuning configuration.
Fine tuning usually deals with the exceptions that are not covered in baseline configuration. This final bit of tweaking represents the work necessary to fit your special needs.
Configuration Testing-
With the help of your SAP consulting team, you segregate your business processes into cycles of related business flows. The cycles serve as independent units that enable you to test specific parts of the business process. You can also work through configuring the SAP implementation guide (IMG). A tool used to assist you in configuring your SAP system in a step by step manner.
Knowledge Transfer-
As the configuration phase comes to a close, it becomes necessary for the Project team to be self-sufficient in their knowledge of the configuration of your SAP system.Knowledge transfer to the configuration team tasked with system maintenance (that is, maintenance of the business processes after Go-live) needs to be completed at this time. In addition, the end users tasked with actually using the system for day-to-day business purposes must be trained.
Phase 4 - Final Preparation
As phase 3 merges into phase 4, you should find yourselves not only in the midst of SAP training, but also in the midst of rigorous functional and stress testing.Phase 4 also concentrates on the fine tuning of your configuration before Go-live and more importantly, the migration of data from your old system or systems to SAP.
Workload testing (including peak volume, daily load, and other forms of stress testing), and integration or functional testing are conducted to ensure the accuracy of your data and the stability of your SAP system. Because you should have begun testing back in phase 2, you do not have too far to go until Go-live.
Now is an important time to perform preventative maintenance checks to ensure optimal performance at your SAP system. At the conclusion of phase 4, take time to plan and document a Go-live strategy. Preparation for Go-live means preparing for your end-users questions as they start actively working on the new SAP system.
Phase 5 - Go-live and Support
The Go-live milestone is itself is easy to achieve; a smooth and uneventful Go-live is another matter altogether. Preparation is the key, including attention to what-if scenarios related not only to the individual business processes deployed but also to the functioning of technology underpinning these business processes and preparation for ongoing support, including maintenance contracts and documented processes and procedures are essential.
| Is This Answer Correct ? | 1 Yes | 0 No |
what is the transaction code for creating shipment cost??
What is the difference between a Sales order and a scheduling agreement?
Can anyone please give an example of writing functional specification for a particular situation?If you can't think of it, here is an example : How do we write a functional specification for the FITGAPS raised in the business system? I know a functional spec, is a detailed description. But realtime gurus, pls give a realtime functional spec for such a situation for me to understand more on this.Thanks a bunch in advance!
how does company knows that vendor deliver the goods to the customer in third party sales process
Hi Experts, Please tell me about the meaning & definition of enhancements along with 7 -10/ as many examples as possible, examples of enhancements with your realtime data live examples from your SAP SD Implementation Project? Plzz guys/ gals I have been asked this question many a times in so many interviews? I need more emphasis on what are the enhancements do you use and how do you use them from your realtime data along with detailed procedure and examples? I request you provide me with any link/ website that would help me in preparing for enhancements along with lots of examples so that I can answer this question easily the next time I face interview It's very urgent. I have interview within 1 or 2 days so, I'm eagerly waiting for your reply. Do reply asap....I would be grateful to you if I get selected in any interview for that matter with your help. Thanks in advance....
6 Answers Cap Gemini, NTT Data,
can we assign shipping point to the sales organization ? in sap r/3 ? if yes how ?
Suppose delivery ,pgi and billing has been done.but we have made a wrong delivery.we want to reverse the document.how?
how we will configure export sales in sd (respect to plants assign and sales process)?
In third party order processing what are the standard G/L A/c's to be posted in ME21?
what is project management ?
what is the idocs and explain steps?
What is the role of SD consultant in Realization phase?
SAP Basis (1262)
SAP ABAP (3939)
SAPScript (236)
SAP SD (Sales & Distribution) (2717)
SAP MM (Material Management) (912)
SAP QM (Quality Management) (99)
SAP PP (Production Planning) (523)
SAP PM (Plant Maintenance) (252)
SAP PS (Project Systems) (138)
SAP FI-CO (Financial Accounting & Controlling) (2766)
SAP HR (Human Resource Management) (1180)
SAP CRM (Customer Relationship Management) (432)
SAP SRM (Supplier Relationship Management) (132)
SAP APO (Advanced Planner Optimizer) (92)
SAP BW (Business Warehouse) (896)
SAP Business Workflow (72)
SAP Security (597)
SAP Interfaces (74)
SAP Netweaver (282)
SAP ALE IDocs (163)
SAP Business One (110)
SAP BO BOBJ (Business Objects) (388)
SAP CPS (Central Process Scheduling) (14)
SAP GTS (Global Trade Services) (21)
SAP Hybris (132)
SAP HANA (700)
SAP PI (Process Integration) (113)
SAP PO (Process Orchestration) (25)
SAP BI (Business Intelligence) (174)
SAP BPC (Business Planning and Consolidation) (38)
SAP BODS (Business Objects Data Services) (49)
SAP BODI (Business Objects Data Integrator) (26)
SAP Ariba (9)
SAP Fiori (45)
SAP EWM (Extended Warehouse Management) (58)
Sap R/3 (150)
SAP FSCM Financial Supply Chain Management (101)
SAP WM (Warehouse Management) (31)
SAP GRC (Governance Risk and Compliance) (64)
SAP MDM (Master Data Management) (0)
SAP MRS (Multi Resource Scheduling) (0)
SAP ESS MSS (Employee Manager Self Service) (13)
SAP CS (Customer Service) (0)
SAP TRM (Treasury and Risk Management) (0)
SAP Web Dynpro ABAP (198)
SAP IBP (Integrated Business Planning) (0)
SAP OO-ABAP (Object Oriented ABAP) (70)
SAP S/4 HANA Finance (Simple Finance) (143)
SAP FS-CD (Collections and Disbursements) (0)
SAP PLM (Product Lifecycle Management) (0)
SAP SuccessFactors (33)
SAP Vistex (0)
SAP ISR (IS Retail) (28)
SAP IdM (Identity Management) (0)
SAP IM (Investment Management) (0)
SAP UI5 (59)
SAP SCM (Supply Chain Management) (51)
SAP XI (Exchange Infrastructure) (49)
SAP Cloud Platform (34)
SAP Testing (89)
SAP SolMan (Solution Manager) (63)
SAP MaxDB (116)
SAP GUI (15)
SAP APO PPDS (50)
SAP AllOther (329)