Answer Posted / devarshi shukla
ASAP stands for Accelerated SAP.
Its purpose is to help design SAP implementation in the most efficient manner possible. Its goal is to effectively optimize time, people, quality and other resources, using a proven methodology to implementation.
The Five Phases of Implementation as under:
Phase 1 Project Preparation
Phase 2 Business Blueprint
Phase 3 Realization
Phase 4 Final Preparation
Phase 5 Go-Live and support
Phase-1 initiates with a retrieval of information and resources. It is an important time to assemble the necessary components for the implementation. Some important milestones that need to be accomplished for phase 1 include
- Obtaining senior-level management/stakeholder support
- Identifying clear project objectives
- Architect an efficient decision-making process
- Creating an environment suitable for change and re-engineering
- Building a qualified and capable project team.
Phase 2- Business Blueprint
SAP has defined a business blueprint phase to help extract pertinent information about your company that is necessary for implementation. These blueprints are in the form of questionnaires that are designed to probe for information that uncovers how your company does business. As such, they also serve to document the implementation.
Each business blueprint document essentially outlines your future business processes and business requirements. The kinds of questions asked are germane to the particular business function, as seen in the following sample questions:
1) What information do you capture on a purchase order?
2) What information is required to complete a purchase order?
Phase- 3 - Realization
With the completion of the business in phase 2, "functional" experts are now ready to begin configuring SAP.
The Realization phase is broken in to two parts.
1) Your SAP consulting team helps you configure your baseline system, called the baseline configuration.
2) Your implementation project team fine-tunes that system to meet all your business and process requirements as part of the fine tuning configuration.
The initial configuration completed during the base line configuration is based on the information that you provided in your blueprint document. The remaining approximately 20% of your configuration that was not tackled during the baseline configuration is completed during the fine tuning configuration.
Fine tuning usually deals with the exceptions that are not covered in baseline configuration. This final bit of tweaking represents the work necessary to fit your special needs.
Configuration Testing-
With the help of your SAP consulting team, you segregate your business processes into cycles of related business flows. The cycles serve as independent units that enable you to test specific parts of the business process. You can also work through configuring the SAP implementation guide (IMG). A tool used to assist you in configuring your SAP system in a step by step manner.
Knowledge Transfer-
As the configuration phase comes to a close, it becomes necessary for the Project team to be self-sufficient in their knowledge of the configuration of your SAP system.Knowledge transfer to the configuration team tasked with system maintenance (that is, maintenance of the business processes after Go-live) needs to be completed at this time. In addition, the end users tasked with actually using the system for day-to-day business purposes must be trained.
Phase 4 - Final Preparation
As phase 3 merges into phase 4, you should find yourselves not only in the midst of SAP training, but also in the midst of rigorous functional and stress testing.Phase 4 also concentrates on the fine tuning of your configuration before Go-live and more importantly, the migration of data from your old system or systems to SAP.
Workload testing (including peak volume, daily load, and other forms of stress testing), and integration or functional testing are conducted to ensure the accuracy of your data and the stability of your SAP system. Because you should have begun testing back in phase 2, you do not have too far to go until Go-live.
Now is an important time to perform preventative maintenance checks to ensure optimal performance at your SAP system. At the conclusion of phase 4, take time to plan and document a Go-live strategy. Preparation for Go-live means preparing for your end-users questions as they start actively working on the new SAP system.
Phase 5 - Go-live and Support
The Go-live milestone is itself is easy to achieve; a smooth and uneventful Go-live is another matter altogether. Preparation is the key, including attention to what-if scenarios related not only to the individual business processes deployed but also to the functioning of technology underpinning these business processes and preparation for ongoing support, including maintenance contracts and documented processes and procedures are essential.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is “characteristic”? How does the term characteristic relate to transaction code cto4?
can you delete order?
Explain what copy control is and when copy control transition can be done? In what manner copy control transition can be done?
Explain about distribution channel?
Explain the assignments among organizational units in sd
How to change chart of accounts of company code after making several sales orders and delivery?
How do you define document numnber ranges
Hello sap tech gurus, please see if you can answer my questons with real life expreiences. 1. Explain me your expreience in customizing with Intercompany Billing? 2. give an example of unit testing and integration testing you have performed in your expreience? 3. While working with Copy control functionality, what exactly did you do within data transfer routines? Please answer any question or all questions possible. Thank you veryyy much in advance!!!. my email is l.mohan89@yahoo.com
how to create sold to party, ship to party in inquiry , quotation in sap sd
How many tickets you have solved till date? can you please elaborate it with solutions?
what is the difference between sap credit memo request and sap credit memo?
Are you familiar with the partner profile setup? I am sure when these EDI transactions must have been posted through SAP as idoc?
Sir, I'Ve interview with IBM . I want few SAP-SD real time tickets and its solution . ... E-Mail New Answers Answer Selected Questions Post New SD Question ...
Name at least five features that you can control for the item category?
What is information structures? What are the basic types of information it (information structure) comprises of?