Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answers were Sorted based on User's Feedback
Answer / a.sanjeevakarna
First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.
in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.
Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.
Steel: Same as above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / viswanadhamklvs
Generally the PVC formula will be given in the Contract
document itself. The month in which the contractor quoted
his bid will be considered as Base month. The indices for
the commodities will be published by the office of Economic
Adviser in the web site eaindustry.nic.in. These index
values shall be substituted in the formulae given against
each commodity viz., steel and cement. In the same fashion,
labour component also shall be considered based on the index
value given by labour Beuro of India.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vamsi
Price escalation can done after completing of total work. As per MB the quantity of cement and steel usage have to recorded
and see the prices in the relevant work done month later total all cement qnty and steel qnty and multiply cement in Kgs/Cum using the data.
Mail me i will give u the Price Escalation Format.
vamsi.talari@gmail.com
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jai
The prise quoted by us in the BOQ wil be the finel prise...
| Is This Answer Correct ? | 0 Yes | 1 No |
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
percentage of wastage limits in construction materials EX : min & max . cement = fine aggregate = coarse aggregate = admixture = wood = tiles = painting = marbles = bricks =
What is code for designing a sheet pile?
how can we find out the ratio of cement and sand in plastering
What is meant by Crystal Concrete?
"Why you consider yourself suitable for the post"
17 Answers Banking, CSE, IIP, IREDA, L&T, Maytas, McHugh, Nations Trust Bank, Teaching, Techkriti IIT Kanpur, Xantium Integrated Solutions,
what is called super elevation of the road?
Design a rectangular channel.
0 Answers CSI, Engineers India Limited,
How does a traffic light signal work ?
1m=3.281feet in that what is .281 mm cm m or anyother
( mean sea level )for which activity we will use this statement?
How much cement and sand required for 9"brick wall per square metre
0 Answers Design Space, Rugipo,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)