Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answer Posted / vamsi
Price escalation can done after completing of total work. As per MB the quantity of cement and steel usage have to recorded
and see the prices in the relevant work done month later total all cement qnty and steel qnty and multiply cement in Kgs/Cum using the data.
Mail me i will give u the Price Escalation Format.
vamsi.talari@gmail.com
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is mean by c32/40s concrete class
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?
How to hide dimensions in autocad?
what is high type road and low type roads
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
What is the withdrawal force of steel nails?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
what is the specific gravity of rubble in plum concert
why & what is perchatage we are using fly ash in concrete?
How to calculate laplength for 3 floors
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
what will be price of 1:2:4pcc per kg?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..