Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answer Posted / a.sanjeevakarna
First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.
in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.
Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.
Steel: Same as above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
Why is concrete cube test carried out?
which has high compressive strength between hollow block and brick masonry?
Which Types Of Bricks ?
why do we not deduct volume of steel to find actual volume of concrete in practical???
Who name us Engineer & Why?
How many litres of water used for curing of 1000sqft of slav
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
What is bmc stands for in bmc software?
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
explain fie benefits of using standard terminology in the measurement process
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm