Trapezoidal section footing calculation of Volume & its Area
Answers were Sorted based on User's Feedback
Answer / sandeep
V=(L X B X d) + h/6(A1 + A2 + 4Am)
L=Length of footing
B=Breadth of footing
d=Depth of bottom portion
h=Height of trapizodial portion (D-d)
A1= Area of bottom portion (L X B)
A2= Area of top portion (l X b )
Am= Mean area of A1 AND A2
Is This Answer Correct ? | 45 Yes | 6 No |
Answer / chandramouli bv
V=(L X B X d) + h/3(A1 + A2 + SQRT(A1 X A2 )
L=Length of footing
B=Breadth of footing
d=Depth of bottom portion
h=Height of trapizodial portion (D-d)
A1= Area of bottom portion (L X B)
A2= Area of top portion (l X b )
Is This Answer Correct ? | 37 Yes | 5 No |
what is the density of compacted earth and jamuna sand
in the construction of residential building what type of tank are used?where?why & what is its purpose?
If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?
.want to know the volume of water for 1.2.4 concert mixing ratio
Sir I am from jntuk R13 regulation...... Is there any chance to leave credits
can any1 mail me IS CODES and quality check sheet of materials..? its urgent plz
how to caluclate sienerge qty in construction in ap
0 Answers Rites, VR Residency,
what mean By core Billing
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
Drar the reinforcement detailing of Internal Hinge ?
What is the amount of cement,sand and course aggregate(jully)(in kgs) required for the RCC of an area of 450 square feet and 5 inch depth if the concrete mixing ratio is 1:2:4(cement:sand:jully)?your answer will be very helpful.
Current ctc and expected ctc? Should i tell or as per Compnany norms? I am not fresher (1 yr exp) so how should i Face it