Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answer Posted / viswanadhamklvs
Generally the PVC formula will be given in the Contract
document itself. The month in which the contractor quoted
his bid will be considered as Base month. The indices for
the commodities will be published by the office of Economic
Adviser in the web site eaindustry.nic.in. These index
values shall be substituted in the formulae given against
each commodity viz., steel and cement. In the same fashion,
labour component also shall be considered based on the index
value given by labour Beuro of India.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What Reinforcements Are Used In The Process Of Prestressing?
What are the different methods for drawing an arc?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
Different sizes of Hollow blocks and its weight. Thanks.
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
Define What are the uses of Groynes?
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
how to nfind out the specific gravity of sand.aggregate,water please help...
Specific gravity of cement?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What is thumb rule for deep trench excavation
Reinforcement details at hinged joint
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
what is the difference between prime coat and tack coat in road construction