Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how can we calculate the amount of concrete in trapezoidal
footing?

Answers were Sorted based on User's Feedback



how can we calculate the amount of concrete in trapezoidal footing?..

Answer / prashant verma

if A is length and B is breath and H is total height of trapezoidal footing and a' and b' is size of column n h is trapezoidal portion height.
then total qty of concrete is=A*B*(H-h)+[{h/3{a^2+b^2+(ab)^1/2}]
where a=A*B
b=a'*b'

Is This Answer Correct ?    6 Yes 2 No

how can we calculate the amount of concrete in trapezoidal footing?..

Answer / ghantola

Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ] where , l = length , b = breadth , d = bottom depth , h = D - d , A1 = bottom area , A2= top area (ii) is = V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1 = bottom area , A2= top area, Am = Mean of Top and Bottom Area 

Is This Answer Correct ?    1 Yes 0 No

how can we calculate the amount of concrete in trapezoidal footing?..

Answer / satya.mvvs

It can be find by averaging method

By averaging the width / length of the the footing

Is This Answer Correct ?    1 Yes 2 No

how can we calculate the amount of concrete in trapezoidal footing?..

Answer / ajay saini

if the area of base is A1 and the area of top is A2 then the volume=h/3(A1squr+A2squr+under the rootA1xA2)
nOW QUANTITY(KG)=Volume x Density of concrete
the density of concrete Varies on different conditions but we can take this 1500-2350 kg/cum

Is This Answer Correct ?    2 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

How to find the requirement of cement and sand for the 1cum of rr masonry work

1 Answers   S Tech,


How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction

0 Answers  


hi guys what happens if you are absent for a supplymentry exam?

0 Answers  


what is the formular for measuring minimum depth of a foundation

3 Answers  


How much wastages taken in 1. cement 2. steel 3. fine aggregate 4. coarse aggregates (10mm, 20 mm)

0 Answers   Wonderla Holidays,


what is the weight of wet concrete?

8 Answers   ABB,


What is full form of SNF base in concrete mix design for admixture percentage?

2 Answers  


What is the density of steel?

6 Answers  


how to calculate steel columns beams and slab please give me brief calculation

14 Answers   Focus, Haven Foundation, Indian Railways, Surya Builders, VICC,


draw the sfd and bmd of catilever beam subjected to point load and udl. plot graphically the difference in deflection pattern of simply supported and cantilever beam subjected to point load.

2 Answers   Microsoft, TCS,


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

0 Answers   L&T,


what is lever arm constent formula?

1 Answers   CGMSC, NSL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)