Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how can we calculate the amount of concrete in trapezoidal
footing?

Answer Posted / prashant verma

if A is length and B is breath and H is total height of trapezoidal footing and a' and b' is size of column n h is trapezoidal portion height.
then total qty of concrete is=A*B*(H-h)+[{h/3{a^2+b^2+(ab)^1/2}]
where a=A*B
b=a'*b'

Is This Answer Correct ?    6 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft

2161


why we use aggregate,sand with cement in concrete?

9818


why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?

11160


when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?

2148


How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?

1665


What are the different types of foundation?

1346


What Are The Different Type Of Slump Test Indications?

1214


What is the diff between cad & cadd?

1174


what is the maximum number of course that can be laid according to IS code and the max height.

2075


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2147


what is the formula to find the diagonal shape stirrups?

1899


What is the substitute of Mastic Asphalt?

8098


What is the strength of cement?

1251


What year was the keystone power plant in Indiana County constructed?

1146


Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)

1878