how can we calculate the amount of concrete in trapezoidal
footing?
Answer Posted / ghantola
Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ] where , l = length , b = breadth , d = bottom depth , h = D - d , A1 = bottom area , A2= top area (ii) is = V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1 = bottom area , A2= top area, Am = Mean of Top and Bottom Area
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
How did the romans get water up hills using aqua ducts?
how is the reinforcement is distributed in triangular slab
List out some of the software program that can be useful for architect?
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
how to calculate quantity of bricks in circular manhole with examples.
What are segregation and bleeding?
How can we make a hole in a solid rectangle using solidsworks?
why we use aggregate,sand with cement in concrete?
Explain the latest method to detect a crack in a building?
Explain what is the difference between built area and super built up area?
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
What is zoning permit?
what post do you prefer to work in this company and why do you think you can serve better in such position?
States some of the tool bars used in cad?