how can we calculate the amount of concrete in trapezoidal
footing?
Answer Posted / ghantola
Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ] where , l = length , b = breadth , d = bottom depth , h = D - d , A1 = bottom area , A2= top area (ii) is = V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1 = bottom area , A2= top area, Am = Mean of Top and Bottom Area
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to calculate spacing rod in column
How many bricks are there in 100cft?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
What are the responsibilities of a construction manager?
specifications of fe500 steel
is basic cost of the material includes tax?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Difference between pre-tensioning and post-tensioning.
How do you change a dimension value in solidsworks?
How can you distinguish between sorption, absorption and adsorption?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
how many digree of freedom in four bar chain
How much cement will require for 1Rmt Skirting laying