sundeep


{ City } hyderabad
< Country > india
* Profession * project manager
User No # 82609
Total Questions Posted # 2
Total Answers Posted # 11

Total Answers Posted for My Questions # 6
Total Views for My Questions # 9369

Users Marked my Answers as Correct # 53
Users Marked my Answers as Wrong # 19
Questions / { sundeep }
Questions Answers Category Views Company eMail

why 50% more is assumed while calculating dry volume of coarse and fine aggregates in concrete calculations.whether 50% more is correct? How is it decided? whether the same is applicable to cement volume. Also what about cement mortar dr volume? How much more is to be considered for dry volume of mortar.

1 Civil Engineering 2511

what is zero slump concrete

5 Civil Engineering 6858




Answers / { sundeep }

Question { L&T, 115763 }

plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?


Answer

The price/rate will depend on grade of materials used and geographical location.

Is This Answer Correct ?    9 Yes 2 No

Question { 5560 }

WHAT IS TEAM SIZE IN CONSTRUCTION WORK


Answer

It is the no. of persons alloted to manage the site at managerial, executive and supervisory levels.

Is This Answer Correct ?    0 Yes 0 No


Question { 7102 }

how many cement bags rquired for solid block construction
for 100 sqft in 1:6 proportion?


Answer

0.7 bags cement for 100 sqft wall

Is This Answer Correct ?    0 Yes 0 No

Question { Bhel, 13560 }

what happened if the diameter of capillary tube is double
then the capillary rise will be


Answer

same

Is This Answer Correct ?    0 Yes 1 No

Question { IVRCL, 233991 }

what is tmc ,term is used in measureing water, pls tell me 1
tmc = how many litres?


Answer

There are 28316846592 liters in 1 TMC of water.

Is This Answer Correct ?    42 Yes 14 No

Question { CCCL, 14504 }

difference between limit state method and working stress in
terms of load


Answer

Working Stress Method
The Stresses in an element is obtained from the working loads and compared with permissible stresses.
The method follows linear stress-strain behaviour of both the materials.
Modular ratio can be used to determine allowable stresses.
Material capabilities are under estimated to large extent. Factor of safety are used in working stress method.
The member is considered as working stress.
Ultimate load carrying capacity cannot be predicted accurately.
The main drawback of this method is that it results in an uneconomical section.
Limit State Method
The stresses are obtained from design loads and compared with design strength.
In this method, it follows linear strain relationship but not linear stress relationship (one of the major difference between the two methods of design).
The ultimate stresses of materials itself are used as allowable stresses.
The material capabilities are not under estimated as much as they are in working stress method. Partial safety factors are used in limit state method.

Is This Answer Correct ?    0 Yes 0 No

Question { Tulip, 8575 }

what is slope provided to floor?


Answer

1:100 for floors

Is This Answer Correct ?    1 Yes 0 No

Question { 11305 }

how can we calculate the amount of concrete in trapezoidal
footing?


Answer

Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ] where , l = length , b = breadth , d = bottom depth , h = D - d , A1 = bottom area , A2= top area (ii) is = V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1 = bottom area , A2= top area, Am = Mean of Top and Bottom Area 

Is This Answer Correct ?    1 Yes 0 No

Question { 5342 }

Is there any possibility of changing in dia of bar from
lower to higher (i.e Lower dia bar at bottom and Higher dia
bar at top)


Answer

yes in cantilevers and inverted beams

Is This Answer Correct ?    0 Yes 0 No

Question { IVRCL, 12091 }

what type of cement are used for fixing of tiles at
floor/wall


Answer

OPC 43 grade cement is more appropriate as I have found sometimes cracks in dado tiles after fixing due to 53 grade cement use, where more heat is produced during reaction with water.

Is This Answer Correct ?    0 Yes 1 No

Question { 18485 }

lap length formula


Answer

48d in tension and 40 d in compression. lap length varies as per grade of concrete and steel

Is This Answer Correct ?    0 Yes 1 No