Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).

Answers were Sorted based on User's Feedback



What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by vol..

Answer / wajahat

dry mix volume=1*1.5=1.5m^3
volume of sand=1.5*(2/7)=0.4285m^3

Is This Answer Correct ?    6 Yes 2 No

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by vol..

Answer / darshandachchu@gmail.com

2*1.54/7=0.44 m3

Is This Answer Correct ?    1 Yes 0 No

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by vol..

Answer / ravi

i have one doubt in quantity calculation.

if we calucalate the quantity of indivisulal material to one cubic meter... if add the all material it excess to the one cubic meter so how it is considering.

pls solve my doubt.

Is This Answer Correct ?    1 Yes 0 No

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by vol..

Answer / saurabh dhanotiya

M15-1:2:4
Total volume-7
Cement required-(1/7)*1.57=.224m^3
Density of cement-1440*.224=322.97 kg/m^3
No of bags-6.45~7 bags
The standard volume of dry mix mortar..1.57
Can check if in it code also

Sand required-(2/7)*1.57=.448×1600=717 kg/m^3

Aggregate required-(4/7)*1.57=.897*1500=1345 kg^3

Water-150-180litr

Is This Answer Correct ?    1 Yes 1 No

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by vol..

Answer / shamsideen mohammed sakwa

1:2:4=7, let's assume the area to be plastered is 100m2
0.012*100=1.2m3
2/7*1.2=0.3428572
You divide your ans by the volume of the tipper per trip,
0.3428572/3.82m3 per single trip
=1.3097145
Approximately = 1.31

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is the method of soil replacement test?

0 Answers  


how to calculate Tile skirting

5 Answers   JMC Projects,


All aptitude question of Bechtel

0 Answers   Bechtel,


Please let me know the name of university which is offered distance education in BE or Btech in direct 3rd samester????

1 Answers   L&T,


In your experience what is the maximum beam length. What's beam size and also please provide column size also. Thanks.

1 Answers  


why crakes are developped in opening corners

3 Answers  


what does 1 in 30 or 1 in 40 mean when constructing camber in roads.

5 Answers   Simplex,


Can we provide lapping of R/f steel for plinth beam in support portion(At column)?

2 Answers  


Why are steel plates inserted inside bearings in elastomeric bearings?

0 Answers  


Clarify the out turn of steel fixer in construction field

2 Answers  


hai.... please any guide me were i can get interview questions& ans for Unigraphics

0 Answers   Construction, TCS,


How to find arc area with using angle?with out using angle?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)