Answer / wajahat
dry mix volume=1*1.5=1.5m^3
volume of sand=1.5*(2/7)=0.4285m^3
| Is This Answer Correct ? | 6 Yes | 2 No |
Answer / ravi
i have one doubt in quantity calculation.
if we calucalate the quantity of indivisulal material to one cubic meter... if add the all material it excess to the one cubic meter so how it is considering.
pls solve my doubt.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / saurabh dhanotiya
M15-1:2:4
Total volume-7
Cement required-(1/7)*1.57=.224m^3
Density of cement-1440*.224=322.97 kg/m^3
No of bags-6.45~7 bags
The standard volume of dry mix mortar..1.57
Can check if in it code also
Sand required-(2/7)*1.57=.448×1600=717 kg/m^3
Aggregate required-(4/7)*1.57=.897*1500=1345 kg^3
Water-150-180litr
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / shamsideen mohammed sakwa
1:2:4=7, let's assume the area to be plastered is 100m2
0.012*100=1.2m3
2/7*1.2=0.3428572
You divide your ans by the volume of the tipper per trip,
0.3428572/3.82m3 per single trip
=1.3097145
Approximately = 1.31
| Is This Answer Correct ? | 0 Yes | 0 No |
How many pyramid in egypt?
Floor tile measurement? Wall to wall or skirting to skirting
Maximum foundation pressure under PRCC box is 19 T/Sqm and net safe bearing capacity is 12.65. Is it safe? pl help me
What are the specification of good quality sand for plaster and brickwork?
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
I need to know the productivity of meason/labour/barbender/carpenter while doing work like Shuttering, reinforcement steel, brick work, earth work?
why we use minimum cement as given in IS mix design code
Calculation of curtain wall of box culvert
How many modular bricks are required for 1 cubic meter of brick masonry?
14 Answers ITI, L&T,
how many nails in 1 kg for 1 inches?
2 Answers Jagson, Shoba Devlopers, Sobha Developers,
how to calculate concrete quantity for footing using M25 grade 1:1:2 for 730cft.
How can we find out the clear cover for a circular ring and rectangular ring..
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)