Answer / santo
Practically we can adopted 6 Number cubes for cube testing.
3 number cubes test on 7th day & other 3 cubes test on 28th
day..
Is This Answer Correct ? | 34 Yes | 0 No |
Answer / rajah
As per IS 7 days is not required but 7 days result is just a cross checking (7 days result must more than 77%)
for 28 days
concrete in cmt no of samples(3 cubes)
1) 1 to 5 1
2) 6 to 15 2
3) 16 to 30 3
4) 31 to 50 4
5) 51 and above 4 plus one additional sample for
each additional 50 cmt
Is This Answer Correct ? | 23 Yes | 9 No |
Answer / santosh kumar namdev
As per IS 456:2000 for 28 days
concrete in cmt no of samples(3 cubes)
1) 1 to 5 1
2) 6 to 15 2
3) 16 to 30 3
4) 31 to 50 4
5) 51 and above 4 plus one additional sample for
each additional 50 cmt Or nomber of 06 sample of concrete
cube 03 of 7Days and 3 of 28 Days individual Avg. compressive
strength +/- 15 %
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / sjtbehera
Yes 3 nos for 7 days and 3 nos for 28days. The avg gets strength
Is This Answer Correct ? | 6 Yes | 2 No |
how many bricks,cement,sand of a 40*30*6 ft bowndry wall?
6 Answers Natco, NGO, OGDCL, SIL, Simplex,
how is calculate the developement length of column such like as L
How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6
Detection of a beam & a girder areββββ
how should i calculate the concrete volume in a circular RCC wall ? what is the formula pls add diagram link for explaing
Dfine superelevation.it depends upon which of the following. 1.surface condition of road 2.width of road 3.radius of curve 4.speed of vehicle
what is Brick crushing strength(PSI)?
What is the crank length in the slab?
1.DIFFERENCE BETWEEN NOMINAL MIX AND DESIGN MIX? 2.WHAT IS MEANT BY STRUCTURAL DESIGN? 3.IN STAAD WHY WE RELEASE MOMENT TO A MEMBER? 4.ON WHAT BASIS PARTIAL FACTOR OF SAFETY ARE DECIDE?FROM THE LOAD COMBINATION? 5.WHY WE PROVIDE EXTRA BAR & DEVELOPEMENT LENGTH AT TOP? 6.FULL FORM OF SPT & SMB? 7.WHAT IS MEANT BY ITP IN A CONSTRUCTION PROJECT? 8.WHAT IS LEAST COUNT OF THEODOLITE SURVEY? 9.WHAT ARE THE CAUSES OF FAILURE OF FOUNDATIONS AND REMEDIAL MEASURES? 10.WHAT ARE THE VALUES OF COMPRESSIVE STRENGTH? 11.STEEL CALCULATION FOR FOOTING,BEAM & SLAB? 12.WHAT IS MEANT BY GANTRY GIRDER? 13.IN SITE HOW WE CAN IDENTIFY THE ONE WAY, TWO WAY SLAB? 14.DIFFERENCE BETWEEN ANCHORAGE LENGTH & DEVELOPEMENT LENGTH? 15.BEARING CAPACITY OF STEEL SHUTTERING?LOAD CARRYING FOR SHUTTERING?
what is the difference between site engineer & site incharge
how many 1st class bricks in 1cu feet?
28 Answers ECCI, Jayant Group, L&T,
what is ment by surveying?