What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).
Answer Posted / shamsideen mohammed sakwa
1:2:4=7, let's assume the area to be plastered is 100m2
0.012*100=1.2m3
2/7*1.2=0.3428572
You divide your ans by the volume of the tipper per trip,
0.3428572/3.82m3 per single trip
=1.3097145
Approximately = 1.31
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to create our resume?
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
what is the design procedure for building
What is the biggest dam in america?
what is the formula to find the diagonal shape stirrups?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
what else we can add rather than admixture in concrete to reduce the cement quantity?
how calucate cement sand ratio for plstering
why does the most of civil engg is not intersted to going for teaching field?