What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).
Answer Posted / shamsideen mohammed sakwa
1:2:4=7, let's assume the area to be plastered is 100m2
0.012*100=1.2m3
2/7*1.2=0.3428572
You divide your ans by the volume of the tipper per trip,
0.3428572/3.82m3 per single trip
=1.3097145
Approximately = 1.31
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
Define What is a projection line?
Slump Values for works?
What is costing in 100squre feet bricks
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
what is the minimum reinforcement provided in beams,footings,slabs? what is the minimum soil bearing capacity to design a multistorey building
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
Can inverted beams used in pipes during construction?
When column of building is abutting the boundary line,then suitable footing advised is
How to calculate the force on a column of three story building. What should be the base concrete height?.
What is thumb rule in quantity and cost estimation of a residential building in civil engineering??
Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.
What is Refuse Area In High Rise Building ?