If any HVDC line is going with positive & negative(the
negative usually have return path of current with earthing
electrode).
Now the question is if this HVDC earthed electrode which is
using as return path and earthed any nearby 400kv or 220kv
AC substation equipments.
which will be the impact of this on AC substation & its
equipment, how severe may be this and what should be the
minimum distance require between HVDC earthed electrode and
AC substation equipments?
It's really an high engineering level question...Dare to
answer and increase your knowledge.
No Answer is Posted For this Question
Be the First to Post Answer
What will be the size of cable required for 5.5 KW motor ( Full load current 10 Amps approx.), Starting current with DOL is 120 Amps. Aprrox. Short circuit current with LLLG fault is 2000 Amps Approx.
where are the circulat the diesel in DG parts name with pictue
how unidirectional torque is produced in DC motor?
what is star&delta connections?
what are the installation procedure of high voltage power transformer,CT,CB&PT?
the parts of transformers ?
1 Answers Bhel, Facility management,
hi frenz,its aswathy.i hve aplied for the hpcl test on feb,pls send the test patern & the placement papers as soon as possible. mail-id :kjaswathy@gmail.com
how to calculate the current carrying capacity of a conductor. How it is related to diameter of cable or conductor
what is capacitor voltage transformer?? how it is different from potential transformer?
How can we convert the motor to generator and also generator to motor
we have one pumping station and 4.6 MW 7 no.s synchronous motors.so there is no required HT capacitor to improve power factor.But we have two no.s of 25 Mva power transformer connect to distribute the power for motors connect with 220 kv line.So i have required the HT capacitor to improve power factor at HT side i mean power transformer bus side.So please suggest how much HT capacitor banks required for same.
Double Busbar Scheme for outdoor switch yard system (132kv) step up power plant Hi friends 1. in this system both busbars energized all the time. 2. what is the meaning of main BB and transfer BB, 3. step up transformer connect main bus bar all the time or both BB connected through DS switch . 4.bus sectionalization means ? thank you.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)