Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answers were Sorted based on User's Feedback
Answer / v.kapil
Concrete get its 50 % strength in 3 days and 66.6% in 7 days
with OPC grade of cement, we designed our structure for
full load including of factor of safety but actually such
loads never come structure in its whole life span, only 40-
50% loads ware accoured during construction so we can
remove our form work after 7-10 days but after confirmation
of cube results of 7 days.
| Is This Answer Correct ? | 15 Yes | 0 No |
Answer / mhbkpr
We cannot deshutter in all type of concrete works. for e.g
footing, plinth, beam sides like we can remove within this.
But roof slab likes we need provide back proping before
removing.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / m.haseeb yaquobi
becuase it reache more then 50% of its full strenght
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / saif raza
As deshuttering period is desrcibe in IS code for diffrent
structural member.
for deshutering purpose minimum strength required is
between 65 to 75% & concrete gain more then 65% atseven
days so it is safe to remove.
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / ankit
concrete achive its full stenghth in 28 days.while minimum
strength accrd. IS CODE is 7day strngth.
in field where the cost of construction is low,
shuttering / formwork is many a times removed even after
two to three days.only intial strenght matters.
| Is This Answer Correct ? | 6 Yes | 8 No |
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
what"s the purpose of damp proof course (DPC)and where it"ll provide?
What is the unit weight of cement,sand,Brick,Reinforcement concrete
What are the dimensions of 1)Standard Brick 2)Nominal Brick What is the difference between them in terms of use ?
49 Answers ASF, Grasim, HSS BIM, JPSC Jharkhand Public Service Commission, L&T, NCC, RNA, SEW Infrastructure, Simplex, TCE,
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
What is the basic difference between QA and QC
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
WHAT TYPE OF MATERIALS (CHEMICALS) ADDED IN CONCRETE TO INCREASE THE STRENGTH OF CONCRETE?
HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC METER.
How do you find the difference between 53&43 grade cement in site?
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)