Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / saif raza
As deshuttering period is desrcibe in IS code for diffrent
structural member.
for deshutering purpose minimum strength required is
between 65 to 75% & concrete gain more then 65% atseven
days so it is safe to remove.
| Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
During reclamation how can the occurrence of mud waves can be rectified?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
what is education Cess.
how to find ssm in foundation?
What is Time period of a building and its relation with frequency ?
How to calculate steel for beam slab and column
psc girder detail
what is mean by reestimation?
how many material required for brickbat water proofing of toilets.
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?
Why should you consider yourself fit to be hired by jindal steel.
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.