Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / v.kapil
Concrete get its 50 % strength in 3 days and 66.6% in 7 days
with OPC grade of cement, we designed our structure for
full load including of factor of safety but actually such
loads never come structure in its whole life span, only 40-
50% loads ware accoured during construction so we can
remove our form work after 7-10 days but after confirmation
of cube results of 7 days.
| Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
What does civil engineering mean?
what is the method used for marking of cantilevers in hirise buildings by using theodolite
what is Brick crushing strength(PSI)?
What do you understand by “preset” during the installation process of bridge bearings?
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
Describe the various methods of concrete curing?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
Give me an example of a time when something you tried to accomplish and failed.
How much material will consume for following specification water tank (9*7.5*6 feet)?
yasser arfatcompleted his degree in civil from which university
what r the precaution for high in atp tempareture,low in atp tempareture
States some of the commonly used commands in cad software’s?
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
what is relation between SPT N value and driving piles after conducting a soil test?
TELL ME THE EQUATION FOR OGEE SPILLWAY