Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / m.haseeb yaquobi
becuase it reache more then 50% of its full strenght
| Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
How much cement,sand,bricks and water needed for 1square metre brick work?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
what is thumb rule for calculating the size of ISMB required for a particular length of span
which formula used for calculate the area of segmental arch?
What are new methods /technologies of pothole patching?
What is aggregate?
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
What are the Types Of DPC and its Thickness used?
How you can use different dimension tools in cad? What are the different dimensions available?
List out some of the software program that can be useful for architect?
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)