Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / m.haseeb yaquobi
becuase it reache more then 50% of its full strenght
| Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
if the nitrates more than 45mg/l in water lead to disease then what is it called
why we are using stub column..? is it possible to construct steel stub column..?
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
plz.show development and anchorage length in simple diagram.
how much quantity of cement,sand and water required for 1 sq feet flooring work .
The portion of a brick cut across the width is called?
What type of tensile strength is handling by crank in beam? Thanks.
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
Define block?
What is made from large rocks, which protects the base of cliffs?
what is cross hair cursor?
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT