Answer / biplab ghosh

shuttering means a shape made before pouring of concrete as
specific size and diamention. This shape is made by
plywood/plate and with proper support.
centring means supporting arrengment of roof slab from
bottom.

Is This Answer Correct ?    137 Yes 23 No

What is the difference between shuttering..

Answer / devi singh

Shuttering is the frame or base provided for RCC structure
while centering is the support for shuttering.

Is This Answer Correct ?    33 Yes 18 No

What is the difference between shuttering..

Answer / joy

shuttering means form work for concreting , and centering means proper positioning of reinforcement with shuttering.

Is This Answer Correct ?    24 Yes 15 No

What is the difference between shuttering..

Answer / sheik.s

Shuttering is the structure prepared by mostly wood or steel
for pouring of concrete. centring is vertical spports for
withstand that..

Is This Answer Correct ?    13 Yes 4 No

What is the difference between shuttering..

Answer / mohammad eqbal

The vertical form work is called shuttering,where as horizontal form work is called as centring.

Is This Answer Correct ?    40 Yes 36 No

What is the difference between shuttering..

Answer / rakesh pattnaik

In answer #6 I don't get the proper solution. As can i say it shuttering if someone is asking me for centring if there are no difference between these words ? My experience says centring is alignment of TMT iron bars to hold and grip the concrete , while shuttering is to keep it(concrete) in proper place as per our required design

Is This Answer Correct ?    5 Yes 3 No

What is the difference between shuttering..

Answer / shamshair ali

the temporary support provided to the form work for supporting component parts of an arch, dome or other roofing structure is called centering


the temporary support beneath and at the sides of precast or cast in-situ concrete work is called shuttering.

Is This Answer Correct ?    6 Yes 4 No

What is the difference between shuttering..

Answer / nitin lahane

Centering is define as a proper arrangement of the Shuttering for giving dimension to structure.

Is This Answer Correct ?    6 Yes 5 No

What is the difference between shuttering..

Answer / ashwini

In vertical member such as columns etc which are supported by the shuttering and the base of the beam etc are supported by centering.
The shuttering can be removed by two or three days but the centering can be removed by only as per the days of beam.

Is This Answer Correct ?    1 Yes 0 No

What is the difference between shuttering..

Answer / mukarram

I Think there is no Difference between the two.. both are
the same..


Formwork is the term given to either temporary or permanent

moulds into which concrete or similar materials are poured.

In the context of concrete construction, the falsework

supports the shuttering moulds.



and same for shuttering also...

Is This Answer Correct ?    12 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate the capacity of Water tank?

7 Answers  


do we decide reinforcement steel , based on bending moment ? give example with continous slab?

0 Answers  


please differentiate duties and responsible for civil site engineer , Quantity suryevor ,Quality control engineer and Planning engineer

1 Answers  


What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)

0 Answers   Reliance,


Why we used ther red bricks for construction..

1 Answers   Lodha,






I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.

0 Answers  


Cement , sand , concrete ration in M30 Grade

1 Answers   ADITI,


Our IDCT industrial cooling tower height is 15 mtres so need to RCC structure stability test as par any IS Standard or Indian act.

1 Answers   Sepco,


What is thickness of RC hume pipes of size, 300mm, 450mm,600mm

1 Answers   L&T,


Which are the Steel tests ?

0 Answers  


How will find compresive strenth of M20,M25,M30 after 7day,8day 28day etc please drive step by step not shot?

2 Answers  


how to find out the quantity of cement sand and aggregate in slab and flooring

1 Answers   L&T, Ramky,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)