What is mean by ITP in a construction project..

Answer / s.srinivas

Inspection and Testing Plan

Is This Answer Correct ?    99 Yes 4 No

What is mean by ITP in a construction project..

Answer / k b babu

ITP means

I-inspection &
T-Test
P-plan
report f0rmet.

Is This Answer Correct ?    62 Yes 2 No

What is mean by ITP in a construction project..

Answer / naeem

ITP = Inspection test plan.

The contents you can find on the google as well for ITP.

Is This Answer Correct ?    33 Yes 3 No

What is mean by ITP in a construction project..

Answer / naushad siddique

ITP stand for Inspection of Test Plan

Is This Answer Correct ?    1 Yes 0 No

What is mean by ITP in a construction project..

Answer / mahesh rao

Inspiration and test plans

Is This Answer Correct ?    1 Yes 4 No

What is mean by ITP in a construction project..

Answer / krishna prasad

INTERNAL TEST PLAN

Is This Answer Correct ?    5 Yes 48 No

Post New Answer

More Civil Engineering Interview Questions

how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?

1 Answers   LiveCon, Sobha Developers,


How many bricks required for 1 cu.m

7 Answers   Navayuga,


cement consumption per square feet in multi storeyed building

9 Answers   Dhar Associates,


Please Clear My doubt . We Can Design the size of the beam by manually by the Length of the beam...What is the technique adopted

0 Answers  


how will calculate the lift load in high rise buildings

0 Answers  






plz send me civil q papers of hpcl

5 Answers   Shell,


what is lap length?

8 Answers   CCCL,


how do you intend to overcome such challenges?

1 Answers   Savanna Energy,


How much percent of steel use in concrete members etc.slab,beam,lintal,colmn,raft fondation according to concrete volume? Kindly reply me I am in dbout plz

3 Answers  


What are the main reasons for conducting pull-out tests for soil nails?

0 Answers  


IF X = Cement ,Fine Aggregate & Coarse Aggregate are in taken in weights for batching. Y= Cement , Fine Aggregate & Coarse Aggregate are taken in volume for batching. Then what will be the relation between X and Y?

2 Answers  


what is polity

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)