What is consumption based planning?
Answers were Sorted based on User's Feedback
Answer / skvell
Consumption-based planning is based on past
consumption-values, statistical procedures for future
requirements. It’s to avoid the shortfall in requirement
determined from reorder point or forecast requirement.
Difference between MRP and Consumption-based planning, MRP
Planning based on gross requirement through the Bill of
Materials, Consumption-based planning based on past
consumption-values.
Is This Answer Correct ? | 23 Yes | 1 No |
Answer / vishwjeet
Consumption based planning is based on your forecasting
report.What Company has manufactured from past 2 years or
from past 3 months. On the basis of certain conditions
forecasting data needs to be maintained in system and
accordingly we plan and manufacture.
Is This Answer Correct ? | 7 Yes | 1 No |
Answer / chingwaro phillip
an procedure that bases its calculations of material
requirements on previous consumption or forecast values
based on a focusting program
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / jobi
can u provide me ur email id's?
I have more doubts to ask u ...
Is This Answer Correct ? | 2 Yes | 2 No |
Answer / riyaj
as i no,
as per the consumption of the material by the consumers
the production will be done at the planet
* more answers welcome
Is This Answer Correct ? | 3 Yes | 8 No |
what is checking group?
what is credit exposure?
What are the special sales document types?
what is L2 and L3 tickets in SLA......
how it looks like inside?
hai all, i want to know about CIN, and how it is configured.
how customer gets delivery dates in 3 rd party process
Explain about minimum value surcharge calculated?
Who will do batch inputs ? will it be done by functional consultant or technical consultant ?
What is the difference between schedule line in sales order and scheduling agreement?
What is item categories in SAP?.and configuring item categories?..
Hi I am looking for SAP SD course . Can someone suggest me where should I join? Thanks Anjali