how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answers were Sorted based on User's Feedback
Answer / lakshmanarajan
The Ratio is 1:2:4 Total = 7
Ingredients of this Mixture is = 1.57
So the qty of Cement is = (1/7) x 1.57 = 0.224 cum
Volume of cement in i cum = 1440kg
therefore required cement = 1440 x 0.224 = 322.56kg
Weight of 1 cement bag is = 50 kg
so 322.56/50 = 6.45Bag
Add 5% for wastage = 6.45 x (5/100) = 6.77 bag required
Qty of Sand = (2/7) x 1.57 = 0.448 cum (1cum = 35.31 cuft)
convert cum to cuft = 0.448*35.31 = 15.18 cuft
Sand is available in unit,so 1 unit = 100 cuft
So required qty of sand is = 15.18/100 = 0.151 unit require
Qty of Aggregate = (4/7) x 1.57 = 0.89cum
Convert cum to cuft = 0.89 * 35.31 = 31.42cuft
sand & Aggregate also available in unit
so above the same as aggregate = 31.42/100 = 0.314 unit require
| Is This Answer Correct ? | 85 Yes | 12 No |
Answer / roys
Ratio of concrete mix =1:2:4 (Calculation for 1cum)
Cement:-
1/7*1.54=.22 cum [1.54for dry volume]
=.22/0.0345
=6.38bags
Sand:-
2/7*.22=0.06cum
=0.06*35.32
=2.12cft
Aggregate:-
4/7*.22=0.13cum
=0.13*35.32
=4.59cft
| Is This Answer Correct ? | 61 Yes | 24 No |
Answer / mr. b.nagaraj
as per is 6.4 bags of cement & 0.86m3 / 30.31cft of 20mm
aggregate & 0.46m3 / 16.25cft of sand requires for 1m3 of
m15 concrete or 1:2:4
| Is This Answer Correct ? | 46 Yes | 21 No |
Answer / javed ashraf
6.22 BAG OF CEMENT IN ONE CUBIC METER
.44 CUM FINE AGGREGATES
.88 CUM COARSE AGGREGATES
| Is This Answer Correct ? | 25 Yes | 9 No |
Answer / prabakar
RCC 1:2:4 -density of cement=1440kg/m3 1m3 =1440/2=720*0.45
=324kg
=324/50=6.48bags
Sand=6.48*1.25
=8.0125cum
=2*8.0125
=16.025cum
Aggregate
=4*8.012
=32.05cum.
| Is This Answer Correct ? | 13 Yes | 3 No |
Answer / zeshan
Simply for 1 cum of ratio 1:2:4
Concrete 1 cum
Sand 1/2 cum
Cement 1/4 cum
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / er. syed layaq ali
practically Material Consumption in M15 1:2:4
Quantity-1 cum
Cement beg - 6 Nos(0.198 cum)
Coarse Sand - 0.396 Cum
Coarse Aggregate 0.792 Cum
| Is This Answer Correct ? | 7 Yes | 5 No |
Answer / n. rajesh guttedar
Materials used for a 1 cum.in the ratio 1:2:4.
Cement. = 6.336 Bags.or ( 0.220 cum. )
Sand. = 0.440 cum.
Aggregate.= 0.879 Cum.
| Is This Answer Correct ? | 7 Yes | 7 No |
differance bet QA & Qc
Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to WATER- CEMENT ratio?
lap lenth
tell me how to calculate by weight and by volume the quantity of cement sand mortar of 1:2
What is the difference between chamfer and fillet?
What is a Quick Sand?
one litre of shuttering oil how much area covered the shuttering?
What in bending moment, if a moment is free end of cantilever beam?
I need to plaster an area of 1500 square meter. how much quantity of cement and sand need for this.?
what is the weight of concrete for 1 cum?
15 Answers Dhenu Infrastructure, L&T,
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
when will the position neutral axis shifted in beams
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)