How du we calculate dry cement (in Bags) for any concrete,
also sand and aggregate? How many bags of cement does 100
cft of concrete 1:2:4 require? Procedure to calculate the
required amount. Also if there is any easy thumb rule to
find out.
Answers were Sorted based on User's Feedback
100*1.54=154 (1.54 for wet to dry)
1+2+4=7 (sum of ratio)
formula:
cement : (154*1)/7=22 cft = 22/1.25=17.60 Bags
sand : (154*2)/7=44 cft
aggregate: (154*4)/7=88 cft
Is This Answer Correct ? | 18 Yes | 2 No |
Esasiest way to calculate the cement content is thumbrule
as if in 1:2:4 concrete there are 8 bags of cement per cum.
of concrete i.e. 35.325 cft concrete 8 bags cemnt
In schedule of rates amount of cement, sand and aggregates
according to their ratios is given.
Is This Answer Correct ? | 10 Yes | 3 No |
How to plan a project
0 Answers Ahluwalia Contracts, SDS,
how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this quantity can be calculated?
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
What is the meaning of RCC NP3 Pipes
Explain what are the phases inspections are done by local authority while construction?
Why are steel plates inserted inside bearings in elastomeric bearing?
productivity of steel fitter per day
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
how much steel provide in 1m cube r.c.c
If 600mm*200mm*150** size bricks comes 55 piece in one cubic meter then how many 230mm*115mm*75 bricks in one cubic meter
how to replace 8mm bar with 10mm bar if the the 8mm bar is not available..???
how can calculate qty of steel required for one or two ways slabs..