How du we calculate dry cement (in Bags) for any concrete,
also sand and aggregate? How many bags of cement does 100
cft of concrete 1:2:4 require? Procedure to calculate the
required amount. Also if there is any easy thumb rule to
find out.

Answers were Sorted based on User's Feedback



How du we calculate dry cement (in Bags) for any concrete, also sand and aggregate? How many bags ..

Answer / muhammad younas

100*1.54=154 (1.54 for wet to dry)
1+2+4=7 (sum of ratio)
formula:
cement : (154*1)/7=22 cft = 22/1.25=17.60 Bags
sand : (154*2)/7=44 cft
aggregate: (154*4)/7=88 cft

Is This Answer Correct ?    18 Yes 2 No

How du we calculate dry cement (in Bags) for any concrete, also sand and aggregate? How many bags ..

Answer / dushyant bansal

Esasiest way to calculate the cement content is thumbrule

as if in 1:2:4 concrete there are 8 bags of cement per cum.
of concrete i.e. 35.325 cft concrete 8 bags cemnt

In schedule of rates amount of cement, sand and aggregates
according to their ratios is given.

Is This Answer Correct ?    10 Yes 3 No

How du we calculate dry cement (in Bags) for any concrete, also sand and aggregate? How many bags ..

Answer / mayank jain

14.28 cft

Is This Answer Correct ?    6 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

How to plan a project

0 Answers   Ahluwalia Contracts, SDS,


how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this quantity can be calculated?

3 Answers  


hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com

0 Answers  


What is the meaning of RCC NP3 Pipes

17 Answers  


Explain what are the phases inspections are done by local authority while construction?

0 Answers  






Why are steel plates inserted inside bearings in elastomeric bearing?

0 Answers   Bechtel,


productivity of steel fitter per day

2 Answers   Shapoorji Pallonji,


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

0 Answers  


how much steel provide in 1m cube r.c.c

3 Answers  


If 600mm*200mm*150** size bricks comes 55 piece in one cubic meter then how many 230mm*115mm*75 bricks in one cubic meter

1 Answers   Bismi Group,


how to replace 8mm bar with 10mm bar if the the 8mm bar is not available..???

3 Answers   CICEF,


how can calculate qty of steel required for one or two ways slabs..

1 Answers   Proscape LLC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16637)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)