How du we calculate dry cement (in Bags) for any concrete,
also sand and aggregate? How many bags of cement does 100
cft of concrete 1:2:4 require? Procedure to calculate the
required amount. Also if there is any easy thumb rule to
find out.
Answer Posted / dushyant bansal
Esasiest way to calculate the cement content is thumbrule
as if in 1:2:4 concrete there are 8 bags of cement per cum.
of concrete i.e. 35.325 cft concrete 8 bags cemnt
In schedule of rates amount of cement, sand and aggregates
according to their ratios is given.
| Is This Answer Correct ? | 10 Yes | 3 No |
Post New Answer View All Answers
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
What is the crank length in the slab?
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
Define block?
what is smart building materials?
howto calculate the quantities of material used in fly ash brick after finding the volume??
brickwork labour rate per cum ?
What are the problems one might face while having a Cantilever balcony?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
Which is the best book for building construction?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.